3005 S CARDIFF AVE 90034
Certificate Information: 3005 S CARDIFF AVE 90034
- Application / Permit
- 23010-10000-00934
- Plan Check / Job No.
- B23LA03934
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONSTRUCT NEW 416 SQ FT (NET) DETACHED ADU PER STATE LAW CA GC 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c), (d) AND (g)
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | NGHI SU |
| Corrections Issued | 3/17/2023 | NGHI SU |
| Quality Review Completed | 3/17/2023 | GARO TELMI |
| Plan Check Approved | 4/11/2023 | NGHI SU |
| Issued | 9/10/2024 | APPLICANT |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
| CofO Issued | 12/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 3/30/2023 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 3/30/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | A 1 Construction & Designs Inc; Lic. No.: 1002697-B | 2817 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/12/2024 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 9/12/2024 | Approved | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/16/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Underground Mechanical | 9/16/2024 | Partial Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 9/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/11/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 10/11/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/11/2024 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 10/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 11/27/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 11/27/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/4/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/4/2024 | Partial Approval | ASHLEY THOMPSON |
| Special/Order Compliance | 12/4/2024 | Partial Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 12/5/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/9/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/9/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 12/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/12/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/16/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/16/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 12/23/2024 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 12/30/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/3/2025 | Approved | AMY COLIN |
| ELECTRICAL-Final | 6/2/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 6/2/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/2/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/1/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 10/1/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 10/1/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/15/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 10/15/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 10/15/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/6/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 11/6/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 11/6/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/14/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 11/14/2025 | Approved | ASHLEY THOMPSON |
| Final | 11/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 11/24/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | ASHLEY THOMPSON |
| Service/Power Release | 11/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 11/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 12/3/2025 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Not Required | ASHLEY THOMPSON |
| Service/Power Release | 12/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 12/3/2025 | Approved | ASHLEY THOMPSON |
| Final | 12/15/2025 | Conditional Approval | ASHLEY THOMPSON |
| Service/Power Release | 12/15/2025 | Approved | ASHLEY THOMPSON |