4441 S BERRYMAN AVE 90230
Certificate Information: 4441 S BERRYMAN AVE 90230
- Application / Permit
- 23010-10000-00916
- Plan Check / Job No.
- B23LA02174
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 2 STORY STRUCTURE WITH GOURND LEVEL GARAGE WITH NEW DETACHED ADU ON 2ND FLOOR, ABOVE THE GARAGE. ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | SUNMIN LEE |
| Corrections Issued | 3/6/2023 | SUNMIN LEE |
| Quality Review Completed | 3/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/18/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 11/27/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 1/8/2024 | SUNMIN LEE |
| Plan Check Approved | 3/4/2024 | SUNMIN LEE |
| Issued | 3/29/2024 | APPLICANT |
| CofO in Progress | 12/19/2025 | WILBER ROSALES |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 4/12/2023 | DINAH GARIN |
| Permit | Cleared | 4/12/2023 | DINAH GARIN |
| Specific Plan | Cleared | 4/12/2023 | ALESSANDRO MERCURI |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | DINAH GARIN |
| Sewer availability | Cleared | 4/17/2023 | DINAH GARIN |
| Low Impact Development (LID) | Cleared | 7/21/2023 | MELINEH AGHAKHABIAN |
| Address approval | Cleared | 10/6/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 10/6/2023 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/20/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bermejo,, Gil Banzon; Lic. No.: C86264 | 2308 MOUNTAIN OAK RD BAKERSFIELD, CA 93311 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/25/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/30/2024 | Approved | JESUS RODRIGUEZ |
| Grounding or Bonding | 4/30/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/1/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 6/3/2024 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/19/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 9/19/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 9/19/2024 | Approved | JESUS PINEDA |
| Sewer | 10/21/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 10/21/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/25/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 11/25/2024 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 11/25/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 11/25/2024 | Corrections Issued | BOBBY KEY |
| MERV13>=Rough | 11/25/2024 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 11/25/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 11/26/2024 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 12/20/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 12/20/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 12/20/2024 | Partial Inspection | JAYLIN GRAVITTE |
| Insulation | 1/6/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 1/21/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 2/25/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/25/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 6/25/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/27/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/27/2025 | Approved | MICHAEL ALLEN |
| Final | 12/10/2025 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 12/10/2025 | Approved | WILBER ROSALES |
| MERV13>=Final | 12/10/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 12/10/2025 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 12/10/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 12/12/2025 | Approved | WILBER ROSALES |
| Final | 12/19/2025 | OK to Issue CofO | WILBER ROSALES |
| Service/Power Release | 12/19/2025 | Approved | WILBER ROSALES |