4441 S BERRYMAN AVE 90230

Certificate Information: 4441 S BERRYMAN AVE 90230

Application / Permit
23010-10000-00916
Plan Check / Job No.
B23LA02174
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW 2 STORY STRUCTURE WITH GOURND LEVEL GARAGE WITH NEW DETACHED ADU ON 2ND FLOOR, ABOVE THE GARAGE. ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 3/29/2024
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 SUNMIN LEE
Corrections Issued 3/6/2023 SUNMIN LEE
Quality Review Completed 3/9/2023 GARO TELMI
Applicant returned to address corrections 10/18/2023 SUNMIN LEE
Applicant returned to address corrections 11/27/2023 SUNMIN LEE
Applicant returned to address corrections 1/8/2024 SUNMIN LEE
Plan Check Approved 3/4/2024 SUNMIN LEE
Issued 3/29/2024 APPLICANT
CofO in Progress 12/19/2025 WILBER ROSALES
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 4/12/2023 DINAH GARIN
Permit Cleared 4/12/2023 DINAH GARIN
Specific Plan Cleared 4/12/2023 ALESSANDRO MERCURI
Eng Process Fee Ord 176,300 Cleared 4/17/2023 DINAH GARIN
Sewer availability Cleared 4/17/2023 DINAH GARIN
Low Impact Development (LID) Cleared 7/21/2023 MELINEH AGHAKHABIAN
Address approval Cleared 10/6/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 10/6/2023 DINAH GARIN
Hydrant and Access approval Cleared 2/20/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Bermejo,, Gil Banzon; Lic. No.: C86264 2308 MOUNTAIN OAK RD      BAKERSFIELD, CA 93311

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 4/25/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 4/30/2024 Approved JESUS RODRIGUEZ
Grounding or Bonding 4/30/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/1/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval JESUS RODRIGUEZ
Deputy Steel/Welding 6/3/2024 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/19/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 9/19/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 9/19/2024 Approved JESUS PINEDA
Underground Mechanical 9/19/2024 Approved JESUS PINEDA
Sewer 10/21/2024 Approved TEMISTOCLES CAAL
Shower Pan 10/21/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/25/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 11/25/2024 Corrections Issued BOBBY KEY
Green Building Rough 11/25/2024 Approved BOBBY KEY
HVAC-Rough 11/25/2024 Corrections Issued BOBBY KEY
MERV13>=Rough 11/25/2024 Approved BOBBY KEY
Verify Sprinkler Sign Off 11/25/2024 Approved BOBBY KEY
Deputy Wood Construction 11/26/2024 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 12/20/2024 Approved BOBBY KEY
HVAC-Rough 12/20/2024 Approved BOBBY KEY
Special/Order Compliance 12/20/2024 Partial Inspection JAYLIN GRAVITTE
Insulation 1/6/2025 Approved JESUS PINEDA
Drywall Nailing 1/21/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 2/25/2025 Approved BOBBY KEY
ELECTRICAL-Final 6/25/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 6/25/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 6/27/2025 Approved MICHAEL ALLEN
PLUMBING-Final 6/27/2025 Approved MICHAEL ALLEN
Final 12/10/2025 Not Ready for Inspection WILBER ROSALES
Green Building Final 12/10/2025 Approved WILBER ROSALES
MERV13>=Final 12/10/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 12/10/2025 Not Ready for Inspection WILBER ROSALES
Smoke Detectors 12/10/2025 Approved WILBER ROSALES
HVAC-Final 12/12/2025 Approved WILBER ROSALES
Final 12/19/2025 OK to Issue CofO WILBER ROSALES
Service/Power Release 12/19/2025 Approved WILBER ROSALES