5516 S CENTRAL AVE 1-29 90011
Certificate Information: 5516 S CENTRAL AVE 1-29 90011
- Application / Permit
- 23010-10000-00915
- Plan Check / Job No.
- B23LA03882
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. NEW 4 STORY WITH ROOF DECK 29 UNITS (100% AFFORDABLE HOUSING 22LI & 6 MI) TYPE VA APARTMENT, PER AB2345 & AB1763 ADDITIONAL INCENTIVES
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Current Status
- Issued on 10/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | KEVIN MORALES |
| Assigned to Zoning Architect | 3/9/2023 | ERIC ROMERO |
| Corrections Issued | 3/21/2023 | KEVIN MORALES |
| Quality Review Completed | 3/22/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 6/1/2023 | KEVIN MORALES |
| Plan Check Approved | 4/22/2024 | KEVIN MORALES |
| Issued | 10/30/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 5/15/2023 | WALLIE JONG |
| Historic Resource Verification | Cleared | 7/25/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 7/26/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 7/26/2023 | LAVEON RIDER |
| Highway dedication | Cleared | 7/28/2023 | WALLIE JONG |
| Trees in Parkway | Cleared | 7/31/2023 | ADALBERTO VERA |
| Redevelopment Project Area | Cleared | 8/1/2023 | SUSAN WONG |
| Building over 36-ft | Cleared | 8/16/2023 | CALOSHA APPROVED |
| Community Plan Implem. Overlay | Cleared | 9/12/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/12/2023 | RIDWAN HARDY |
| Density Bonus | Cleared | 9/14/2023 | JAMES MCCARTHY |
| SB8 RUD | Cleared | 9/14/2023 | JAMES MCCARTHY |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | TERRY PHAN |
| Miscellaneous | Cleared | 11/2/2023 | DAVID URITA |
| Miscellaneous | Cleared | 11/2/2023 | DAVID URITA |
| Miscellaneous | Cleared | 11/2/2023 | DAVID URITA |
| Community Plan Implem. Overlay | Cleared | 11/16/2023 | MOHAMMAD HASAN |
| Fire Marshal Fire Life Safety | Cleared | 12/14/2023 | RONILO MULAWIN |
| Sewer availability | Cleared | 12/28/2023 | WALLIE JONG |
| DAS Clearance | Cleared | 1/10/2024 | KEVIN MORALES |
| Frnt yard landscape/Water mgmt | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Opn space landscape/Water mgmt | Cleared | 1/10/2024 | DAVID URITA |
| Low Impact Development (LID) | Cleared | 1/12/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 1/13/2024 | ADRIAN SANCHEZ |
| Green Code | Cleared | 2/16/2024 | AARON COSTA |
| Community Plan Implem. Overlay | Cleared | 3/19/2024 | ANACANY HURTADO |
| Zoning Plan Check | Cleared | 4/1/2024 | ERIC ROMERO |
Contact Information
| Contractor | Ces4 Construction; Lic. No.: 1042127-B | , |
| Contractor | Ces4; Lic. No.: 1042127-B | , |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/10/2025 | Conditional Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/10/2025 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/16/2025 | Partial Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 10/24/2025 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/28/2025 | Partial Approval | RAFAEL CORTES |
| Masonry Wall/Backfill | 10/28/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Partial Approval | JAMES POWERS |
| Green Building Rough | 11/26/2025 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/26/2025 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 12/9/2025 | Partial Approval | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 12/9/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 12/9/2025 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 12/18/2025 | Conditional Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 12/19/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 12/19/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 12/19/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Partial Approval | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 3/5/2026 | Conditional Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 3/9/2026 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/9/2026 | Corrections Issued | JOEY BUCHANAN |
| Grading Pre-Inspection | 3/10/2026 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 3/10/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 3/26/2026 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 5/22/2026 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 5/27/2026 | Partial Approval | JOEY BUCHANAN |
| Insulation | 5/29/2026 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 6/5/2026 | No Result Entered | JAMES POWERS |