1917 S FEDERAL AVE 90025
Certificate Information: 1917 S FEDERAL AVE 90025
- Application / Permit
- 23010-10000-00906
- Plan Check / Job No.
- B23LA03845
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NEW SINGLE FAMILY DWELLING AT FRONT WITH ATTACHED GARAGE
- Permit Issued
- Issued on 3/21/2024
- Issuing Office
- Current Status
- CofO Issued on 6/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | KEVIN MORALES |
| Corrections Issued | 3/13/2023 | KEVIN MORALES |
| Quality Review Completed | 3/14/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 4/18/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 6/20/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 11/6/2023 | KEVIN MORALES |
| Plan Check Approved | 3/12/2024 | KEVIN MORALES |
| Issued | 3/21/2024 | APPLICANT |
| CofO in Progress | 6/5/2025 | KIRK SANDERS |
| Permit Finaled | 6/9/2025 | RICHARD STEINBACH |
| CofO Issued | 6/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2023 | DINAH GARIN |
| Highway dedication | Cleared | 3/22/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 5/31/2023 | ALESSANDRO MERCURI |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 6/1/2023 | AHMED AMARRAGY |
| Hydrant and Access approval | Cleared | 10/25/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 10/27/2023 | MARTIN FRAGOSO |
| SB8 RUD | Cleared | 10/30/2023 | SAMANTHA RIVERA |
| Roof/Waste drainage to street | Cleared | 11/2/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 5/31/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 6/6/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/29/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 7/29/2024 | Corrections Issued | KIRK SANDERS |
| Wood Frame | 8/28/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | KEVIN SARGSYAN |
| Pre-Inspection | 9/10/2024 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/25/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/25/2024 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 10/22/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 10/23/2024 | Approved | KIRK SANDERS |
| Shower Pan | 10/23/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 10/30/2024 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 10/30/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/8/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/8/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 11/25/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/3/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 12/6/2024 | Approved | KIRK SANDERS |
| Sewer | 2/24/2025 | Approved | REGINA MENDEZ |
| PLUMBING-Final | 4/7/2025 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 4/7/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 4/11/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 4/23/2025 | Approved | KIRK SANDERS |
| Deputy Other (see comments) | 4/29/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/29/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 4/29/2025 | Conditional Approval | MICHAEL PELHAM |
| Service/Power Release | 4/29/2025 | Approved | MICHAEL PELHAM |
| Final | 5/5/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 5/5/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Required | KIRK SANDERS |
| Smoke Detectors | 5/5/2025 | Approved | KIRK SANDERS |
| Final | 6/5/2025 | OK to Issue CofO | KIRK SANDERS |