136 W 108TH ST 90061

Certificate Information: 136 W 108TH ST 90061

Application / Permit
23010-10000-00865
Plan Check / Job No.
B23LA03560
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 23'-9" x 30'-0" Detached Accessory Dwelling unit (714 sq.ft.) per GCS 65852.2(e)(1)(B) and GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g). All work per WFPP.
Permit Issued
Issued on 4/11/2023
Issuing Office
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2023 APPLICANT
Assigned to Plan Check Engineer 3/7/2023 AMY GUEVARRA
Corrections Issued 3/8/2023 AMY GUEVARRA
Applicant returned to address corrections 4/5/2023 AMY GUEVARRA
Plan Check Approved 4/8/2023 SARKIS HARABEDIAN
Issued 4/11/2023 APPLICANT
CofO in Progress 8/6/2024 JOSEPH MCGARRY
Permit Finaled 8/7/2024 ANSON MAGLASANG
CofO Issued 8/7/2024 ANSON MAGLASANG
Permit Finaled 8/7/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/21/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 3/21/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 3/29/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 3/29/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 3/31/2023 JEANIE LAM

Contact Information

Contractor L P Design & Construction; Lic. No.: 901296-B       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/17/2023 Approved JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 5/22/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 5/22/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/12/2023 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Corrections Issued JAMES CHAVEZ
HVAC-Rough 6/12/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 6/12/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 6/12/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/13/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/21/2023 Approved JAMES CHAVEZ
Green Building Rough 6/21/2023 Approved JAMES CHAVEZ
HVAC-Rough 6/21/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 6/21/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/23/2023 Approved JAMES CHAVEZ
HVAC-Rough 6/23/2023 Approved JAMES CHAVEZ
Insulation 6/23/2023 Approved JAMES CHAVEZ
Drywall Nailing 7/6/2023 Corrections Issued JAMES CHAVEZ
Drywall Nailing 7/11/2023 Corrections Issued JAMES CHAVEZ
Gas Test 7/11/2023 Not Ready for Inspection JAMES CHAVEZ
Interior/Exterior Lathing 7/11/2023 Not Ready for Inspection JAMES CHAVEZ
Drywall Nailing 7/21/2023 Corrections Issued JAMES CHAVEZ
Drywall Nailing 7/24/2023 Approved JAMES CHAVEZ
Gas Test 7/24/2023 Approved JAMES CHAVEZ
Insulation 7/24/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/24/2023 Partial Approval JAMES CHAVEZ
Interior/Exterior Lathing 8/4/2023 Approved JAMES CHAVEZ
Shower Pan 8/4/2023 Partial Approval JAMES CHAVEZ
Shower Pan 8/29/2023 Approved JAMES CHAVEZ
Underground Mechanical 1/2/2024 Corrections Issued JOHN KLARIN
Underground Mechanical 1/5/2024 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 1/11/2024 Not Ready for Inspection JOHN KLARIN
Final 1/11/2024 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Not Ready JOHN KLARIN
Service/Power Release 1/11/2024 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 1/11/2024 Partial Approval JOHN KLARIN
Underground Mechanical 1/11/2024 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Not Ready JAMES CHAVEZ
BUILDING-Rough-Frame 7/17/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 7/17/2024 Corrections Issued BEN MOLSTAD
Final 7/17/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 7/17/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 7/17/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 7/17/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 7/17/2024 Corrections Issued BEN MOLSTAD
Final 7/23/2024 Corrections Issued JAMES CHAVEZ
Special/Order Compliance 7/23/2024 Not Ready for Inspection JAMES CHAVEZ
Final 7/29/2024 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 7/29/2024 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 7/29/2024 Approved JOSEPH MCGARRY
Final 8/1/2024 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 8/1/2024 Not Required JOSEPH MCGARRY