136 W 108TH ST 90061
Certificate Information: 136 W 108TH ST 90061
- Application / Permit
- 23010-10000-00865
- Plan Check / Job No.
- B23LA03560
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 23'-9" x 30'-0" Detached Accessory Dwelling unit (714 sq.ft.) per GCS 65852.2(e)(1)(B) and GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g). All work per WFPP.
- Permit Issued
- Issued on 4/11/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2023 | AMY GUEVARRA |
| Corrections Issued | 3/8/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 4/5/2023 | AMY GUEVARRA |
| Plan Check Approved | 4/8/2023 | SARKIS HARABEDIAN |
| Issued | 4/11/2023 | APPLICANT |
| CofO in Progress | 8/6/2024 | JOSEPH MCGARRY |
| Permit Finaled | 8/7/2024 | ANSON MAGLASANG |
| CofO Issued | 8/7/2024 | ANSON MAGLASANG |
| Permit Finaled | 8/7/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 3/21/2023 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/31/2023 | JEANIE LAM |
Contact Information
| Contractor | L P Design & Construction; Lic. No.: 901296-B | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/17/2023 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/22/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Rough | 6/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/12/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 6/12/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/13/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/21/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 6/21/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 6/21/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/21/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/23/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 6/23/2023 | Approved | JAMES CHAVEZ |
| Insulation | 6/23/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/6/2023 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 7/11/2023 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 7/11/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/11/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 7/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 7/24/2023 | Approved | JAMES CHAVEZ |
| Gas Test | 7/24/2023 | Approved | JAMES CHAVEZ |
| Insulation | 7/24/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/24/2023 | Partial Approval | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/4/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 8/4/2023 | Partial Approval | JAMES CHAVEZ |
| Shower Pan | 8/29/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 1/2/2024 | Corrections Issued | JOHN KLARIN |
| Underground Mechanical | 1/5/2024 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/11/2024 | Not Ready for Inspection | JOHN KLARIN |
| Final | 1/11/2024 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 1/11/2024 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 1/11/2024 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 1/11/2024 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 7/17/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 7/17/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/17/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 7/17/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 7/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 7/17/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 7/23/2024 | Corrections Issued | JAMES CHAVEZ |
| Special/Order Compliance | 7/23/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 7/29/2024 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 7/29/2024 | Approved | JOSEPH MCGARRY |
| Final | 8/1/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 8/1/2024 | Not Required | JOSEPH MCGARRY |