1465 N DONHILL DR 90210
Certificate Information: 1465 N DONHILL DR 90210
- Application / Permit
- 23010-10000-00851
- Plan Check / Job No.
- B23LA03519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New Single Family Dwelling with an attached garage
- Permit Issued
- Issued on 6/4/2024
- Issuing Office
- Current Status
- Issued on 6/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | CARLOS MONTES |
| Corrections Issued | 3/6/2023 | CARLOS MONTES |
| Quality Review Completed | 3/7/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/2/2023 | CARLOS MONTES |
| Plan Check Approved | 6/9/2023 | CARLOS MONTES |
| Issued | 6/4/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/16/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/16/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/16/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/16/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Sewer availability | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 3/17/2023 | YINGSHI HUANG |
| Distance to fire station | Cleared | 4/22/2023 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 4/22/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 5/9/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/10/2023 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 6/9/2023 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 6/9/2023 | CARLOS MONTES |
Contact Information
| Architect | Whipple,, Marc Evan; Lic. No.: C17132 | 15233 VENTURA BLVD SUITE PH9 SHERMAN OAKS, CA 91403 |
| Contractor | Tallen & Tyce Development Inc; Lic. No.: 1029383-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/20/2024 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 7/17/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/18/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 7/19/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/22/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/15/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/16/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 9/4/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/19/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/30/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 11/14/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Shotcrete | 11/18/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 12/10/2024 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 12/12/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/23/2024 | Partial Approval | SEAN HAUPT |
| Deputy Other (see comments) | 12/24/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/16/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 1/21/2025 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | SEAN HAUPT |
| Deputy Wood Construction | 3/11/2025 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 4/11/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 5/8/2025 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 5/14/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 6/2/2025 | Partial Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/12/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 6/18/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 6/25/2025 | Partial Approval | SEAN HAUPT |
| Gas Test | 6/25/2025 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 6/25/2025 | Approved | SEAN HAUPT |
| Shower Pan | 7/1/2025 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 7/7/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/7/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/16/2025 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 7/16/2025 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 7/16/2025 | Not Ready for Inspection | HENRY KIM |
| Verify Sprinkler Sign Off | 7/16/2025 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 7/18/2025 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 7/18/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/18/2025 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 7/18/2025 | Approved | SEAN HAUPT |
| Insulation | 7/25/2025 | Approved | SEAN HAUPT |
| Drywall Nailing | 8/4/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 8/8/2025 | Approved | JAYLIN GRAVITTE |
| HVAC-Final | 2/26/2026 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 3/10/2026 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/12/2026 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/29/2026 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/29/2026 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/5/2026 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/5/2026 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 5/5/2026 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/7/2026 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 5/13/2026 | Approved | CARLOS MATAMOROS |