3257 W DESCANSO DR 90026
Certificate Information: 3257 W DESCANSO DR 90026
- Application / Permit
- 23010-10000-00836
- Plan Check / Job No.
- B23LA03493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- eplan (N) 10' x 12' DETACHED RECREATION ROOM
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/7/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/1/2023 | ISIS ARGUETA |
| Plan Check Approved | 6/2/2023 | ISIS ARGUETA |
| No Progress | 6/2/2023 | ISIS ARGUETA |
| Plan Check Approved | 6/2/2023 | ISIS ARGUETA |
| Issued | 6/7/2023 | APPLICANT |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/16/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2023 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 6/1/2023 | TINA MIRANDA |
| Grading Pre-Inspection | Cleared | 6/1/2023 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sparks,, David Michael; Lic. No.: C65739 | 2996 SLY FOX CIRCLE ELIZABETH, CO 80107 |
| Engineer | Sparks,, David Michael; Lic. No.: NA65739 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/1/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 12/8/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/16/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/16/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/16/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/16/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/17/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/17/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/18/2024 | Approved | FREDDIE RIVERA |
| Final | 2/29/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 2/29/2024 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 2/29/2024 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 2/29/2024 | Approved | FREDDIE RIVERA |
| Final | 7/17/2024 | Conditional Approval | CRAIG VAUGHAN |
| Service/Power Release | 7/17/2024 | Approved | CRAIG VAUGHAN |