3257 W DESCANSO DR 90026

Certificate Information: 3257 W DESCANSO DR 90026

Application / Permit
23010-10000-00836
Plan Check / Job No.
B23LA03493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
eplan (N) 10' x 12' DETACHED RECREATION ROOM
Permit Issued
Issued on 6/7/2023
Issuing Office
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 MOHAMMAD ESMAILI
Corrections Issued 3/7/2023 MOHAMMAD ESMAILI
Plan Check Approved 6/1/2023 ISIS ARGUETA
Plan Check Approved 6/2/2023 ISIS ARGUETA
No Progress 6/2/2023 ISIS ARGUETA
Plan Check Approved 6/2/2023 ISIS ARGUETA
Issued 6/7/2023 APPLICANT
CofO Issued 7/22/2024 DEROLD HAUFF
Permit Finaled 7/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/16/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/22/2023 ADRIAN SANCHEZ
Construction near power lines Cleared 6/1/2023 TINA MIRANDA
Grading Pre-Inspection Cleared 6/1/2023 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Sparks,, David Michael; Lic. No.: C65739 2996 SLY FOX CIRCLE      ELIZABETH, CO 80107
Engineer Sparks,, David Michael; Lic. No.: NA65739       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 12/1/2023 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 12/8/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 1/16/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 1/16/2024 Approved FREDDIE RIVERA
Green Building Rough 1/16/2024 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 1/16/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/17/2024 Approved FREDDIE RIVERA
Drywall Nailing 1/17/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Approved FREDDIE RIVERA
Green Building Rough 1/17/2024 Approved FREDDIE RIVERA
Drywall Nailing 1/18/2024 Approved FREDDIE RIVERA
Final 2/29/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 2/29/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/29/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 2/29/2024 Approved FREDDIE RIVERA
Final 7/17/2024 Conditional Approval CRAIG VAUGHAN
Service/Power Release 7/17/2024 Approved CRAIG VAUGHAN