4218 1/4-1/2 E ABNER ST 90032

Certificate Information: 4218 1/4-1/2 E ABNER ST 90032

Application / Permit
23010-10000-00834
Plan Check / Job No.
B23LA03486
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) ONE STORY (28'-5" x 51'-11") DETACHED 2 ADUS PER 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) ]. ALL WORK PER ENG. BUILDING TO BE SPRINKLERED WITH NFPA-13D SPRINKLERS.
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2023 APPLICANT
Assigned to Plan Check Engineer 3/7/2023 LUISANGEL VALENZUELA
Corrections Issued 3/8/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/10/2023 SUNMIN LEE
Applicant returned to address corrections 5/30/2023 SUNMIN LEE
Applicant returned to address corrections 6/22/2023 SUNMIN LEE
Applicant returned to address corrections 7/6/2023 VICTOR CHEN
Plan Check Approved 7/7/2023 VICTOR CHEN
Issued 7/26/2023 APPLICANT
CofO in Progress 7/5/2024 LILIANA PORTILLO
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/5/2023 TINA MIRANDA
Address approval Cleared 4/6/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/11/2023 WALLIE JONG
Sewer availability Cleared 4/11/2023 WALLIE JONG
Low Impact Development (LID) Cleared 5/4/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 5/8/2023 JEANIE LAM
GPI Written Notices Cleared 5/30/2023 LUISANGEL VALENZUELA
Grading Pre-Inspection Cleared 5/30/2023 LUISANGEL VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Kaballo,, Amir; Lic. No.: C90707 152 S SWALL DR      BEVERLY HILLS, CA 90211

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/31/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 8/7/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 8/14/2023 Conditional Approval AMY COLIN
ELECTRICAL-Rough 10/20/2023 Approved ROY SPAULDING
HVAC-Rough 10/20/2023 Corrections Issued ROY SPAULDING
PLUMBING-Rough 10/20/2023 Approved ROY SPAULDING
Wood Frame 10/20/2023 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 10/31/2023 Approved AMY COLIN
Green Building Rough 10/31/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 10/31/2023 Approved AMY COLIN
Verify Sprinkler Sign Off 10/31/2023 Approved AMY COLIN
Insulation 11/7/2023 Approved AMY COLIN
Interior/Exterior Lathing 11/7/2023 Partial Approval AMY COLIN
Drywall Nailing 11/20/2023 Approved BRENDAN MORELLI
Green Building Rough 11/20/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/20/2023 Approved BRENDAN MORELLI
Shower Pan 11/20/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 3/1/2024 Corrections Issued LILIANA PORTILLO
Final 3/1/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 3/1/2024 Approved LILIANA PORTILLO
Green Building Final 3/1/2024 Approved LILIANA PORTILLO
HVAC-Final 3/1/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 3/1/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 3/1/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 3/1/2024 Conditional Approval LILIANA PORTILLO
Final 5/10/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 5/10/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 5/10/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved LILIANA PORTILLO
Service/Power Release 5/10/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/10/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/27/2024 Approved LILIANA PORTILLO
Final 6/27/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 6/27/2024 Approved LILIANA PORTILLO
Service/Power Release 6/27/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 6/27/2024 Approved LILIANA PORTILLO