5168 N TOWNSEND AVE 90041

Certificate Information: 5168 N TOWNSEND AVE 90041

Application / Permit
23010-10000-00831
Plan Check / Job No.
B23LA03474
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED TWO STORY ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 12/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 MICHAEL LOPEZ
Corrections Issued 3/9/2023 MICHAEL LOPEZ
Plan Check Approved 5/18/2023 FARSHAD ALIMOHAMADI
Issued 5/19/2023 APPLICANT
CofO in Progress 12/12/2024 ROY SPAULDING
Permit Finaled 12/29/2024 DEROLD HAUFF
CofO Issued 12/29/2024 DEROLD HAUFF
Permit Finaled 12/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/17/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/20/2023 TREVOR QUAN
Sewer availability Cleared 3/20/2023 TREVOR QUAN
Hydrant and Access approval Cleared 3/24/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 4/24/2023 TREVOR QUAN
GPI Written Notices Cleared 5/18/2023 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 5/18/2023 MICHAEL LOPEZ

Contact Information

Architect Williams,, Willard Eugene; Lic. No.: C33989 190 N ROSS LN      MEDFORD, OR 97501
Contractor Golden Age Construction Inc; Lic. No.: 1040171-B 8265 SUNSET BLVD UNIT 205      WEST HOLLYWOOD, CA 90046
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/18/2023 Partial Approval CRAIG VAUGHAN
Sewer 7/18/2023 Approved CRAIG VAUGHAN
Pre-Inspection 7/19/2023 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 7/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/26/2023 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/17/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 8/17/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/12/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 12/12/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/12/2023 Approved CRAIG VAUGHAN
HVAC-Rough 12/12/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 12/12/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/12/2023 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 12/14/2023 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/19/2023 Conditional Approval BRENDAN MORELLI
HVAC-Rough 12/19/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 12/19/2023 Approved BRENDAN MORELLI
Insulation 1/16/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/16/2024 Partial Approval CRAIG VAUGHAN
Drywall Nailing 1/22/2024 Not Ready for Inspection ROY SPAULDING
Drywall Nailing 1/23/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/15/2024 Approved JOSH MEISTER
Shower Pan 2/15/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 10/24/2024 Approved ROY SPAULDING
Final 10/24/2024 Corrections Issued ROY SPAULDING
Green Building Final 10/24/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 10/24/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 10/24/2024 Approved ROY SPAULDING
Final 11/13/2024 Conditional Approval ROY SPAULDING
Service/Power Release 11/13/2024 Approved ROY SPAULDING
Final 12/11/2024 OK to Issue CofO ROY SPAULDING