830 N ALAMEDA ST 90744

Certificate Information: 830 N ALAMEDA ST 90744

Application / Permit
23010-10000-00825
Plan Check / Job No.
B23LA03462
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED 1-SOTRY OFFICE BUILDING. 1 OF 2
Permit Issued
Issued on 9/10/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 MICHAEL LOPEZ
Corrections Issued 3/16/2023 MICHAEL LOPEZ
Quality Review Completed 3/24/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 6/21/2023 MICHAEL LOPEZ
Disabled Access Plans Picked Up 6/21/2023 APPLICANT
Applicant returned to address corrections 7/19/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/24/2024 MICHAEL LOPEZ
Plan Check Approved 6/24/2024 MICHAEL LOPEZ
No Progress 6/24/2024 MICHAEL LOPEZ
Plan Check Approved 9/10/2024 MICHAEL LOPEZ
Issued 9/10/2024 APPLICANT
CofO in Progress 10/10/2025 RICARDO ROBLES
Permit Finaled 11/5/2025 DAVID TSAU
Permit Finaled 11/5/2025 DAVID TSAU
CofO Issued 11/5/2025 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 10/23/2023 KHAING AYE
Highway dedication Cleared 10/23/2023 KHAING AYE
Permit Cleared 10/23/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 11/13/2023 KHAING AYE
Sewer availability Cleared 11/13/2023 KHAING AYE
Trees in Parkway Cleared 11/27/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 12/15/2023 GILBERT URREA
Roof/Waste drainage to street Cleared 1/17/2024 KHAING AYE
DAS Clearance Cleared 3/22/2024 MICHAEL LOPEZ
Green Code Cleared 6/3/2024 MICHAEL LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Preciado,, Noe; Lic. No.: C88426 866 W 10TH      SAN PEDRO, CA 90731

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2025 Corrections Issued JOEY BUCHANAN
Footing/Foundation/Slab 5/6/2025 Approved RICARDO ROBLES
METHANE-Barrier 5/6/2025 Approved RICARDO ROBLES
METHANE-Subgrade 5/6/2025 Approved RICARDO ROBLES
Green Building Rough 6/2/2025 Approved RICARDO ROBLES
METHANE-Rough 6/2/2025 Approved RICARDO ROBLES
Verify Sprinkler Sign Off 6/2/2025 Approved RICARDO ROBLES
Wood Frame 6/2/2025 Partial Approval RICARDO ROBLES
Insulation 6/11/2025 Approved RICARDO ROBLES
Interior/Exterior Lathing 6/11/2025 Approved RICARDO ROBLES
Drywall Nailing 6/24/2025 Partial Inspection RICARDO ROBLES
Pre-Inspection 7/25/2025 Partial Approval RICARDO ROBLES
Reinforced Concrete Frame 8/4/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 8/12/2025 Partial Approval JOEY BUCHANAN
Final 10/2/2025 OK to Issue CofO RICARDO ROBLES
Green Building Final 10/2/2025 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 10/2/2025 Approved RICARDO ROBLES
Wood Frame 10/2/2025 Approved RICARDO ROBLES