230 W 46TH ST 90037

Certificate Information: 230 W 46TH ST 90037

Application / Permit
23010-10000-00812
Plan Check / Job No.
B23LA03370
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) CONSTRUCTION OF TWO STROY DETACHED ADU 1,196 SQ FT (23'X27') AT REAR OF LOT. SEE COMMENT.
Permit Issued
Issued on 10/12/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 TSE MING HUANG
Corrections Issued 3/28/2023 TSE MING HUANG
Quality Review Completed 3/29/2023 KEN GILL
Building Plans Picked Up 4/14/2023 APPLICANT
Applicant returned to address corrections 9/7/2023 TSE MING HUANG
Applicant returned to address corrections 9/11/2023 TSE MING HUANG
Plan Check Approved 10/11/2023 TSE MING HUANG
Issued 10/12/2023 APPLICANT
CofO in Progress 5/15/2025 ALEJANDRO DE ARTOLA
Permit Finaled 5/18/2025 DEROLD HAUFF
CofO Issued 5/18/2025 DEROLD HAUFF
Permit Finaled 5/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 7/10/2023 RIDWAN HARDY
Construction within easement Cleared 7/10/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/18/2023 TOMMY YIN
Address approval Cleared 8/21/2023 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 8/21/2023 JOSEPH RHYU
Roof/Waste drainage to street Cleared 8/21/2023 JOSEPH RHYU
Sewer availability Cleared 8/21/2023 JOSEPH RHYU
Hydrant and Access approval Cleared 10/2/2023 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/26/2023 Corrections Issued ENRIQUE MIRELES
Sewer 1/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/18/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/8/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Corrections Issued CRAIG DAVIS
Gas Test 3/19/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 3/19/2024 Corrections Issued CRAIG DAVIS
Wood Frame 3/19/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Approval DAVID FEILER
Gas Test 3/21/2024 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 3/21/2024 Partial Approval DAVID FEILER
Wood Frame 3/21/2024 Partial Approval DAVID FEILER
Insulation 3/27/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/27/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 5/7/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/9/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/16/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/16/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/16/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/22/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/22/2024 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 5/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/24/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/24/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/24/2024 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 5/24/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/31/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 5/31/2024 Approved JOSH MEISTER
Final 9/18/2024 No Access for Inspection WILLIAM SIERRA
Green Building Final 9/18/2024 No Access for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 9/18/2024 SGSOV Not Ready WILLIAM SIERRA
Service/Power Release 9/18/2024 No Access for Inspection WILLIAM SIERRA
Smoke Detectors 9/18/2024 No Access for Inspection WILLIAM SIERRA
ELECTRICAL-Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 12/5/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/5/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/5/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/6/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/7/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 5/7/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 5/7/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 5/13/2025 Approved ALEJANDRO DE ARTOLA
Final 5/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/13/2025 Approved ALEJANDRO DE ARTOLA
Final 5/14/2025 OK to Issue CofO ALEJANDRO DE ARTOLA