230 W 46TH ST 90037
Certificate Information: 230 W 46TH ST 90037
- Application / Permit
- 23010-10000-00812
- Plan Check / Job No.
- B23LA03370
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) CONSTRUCTION OF TWO STROY DETACHED ADU 1,196 SQ FT (23'X27') AT REAR OF LOT. SEE COMMENT.
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | TSE MING HUANG |
| Corrections Issued | 3/28/2023 | TSE MING HUANG |
| Quality Review Completed | 3/29/2023 | KEN GILL |
| Building Plans Picked Up | 4/14/2023 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | TSE MING HUANG |
| Applicant returned to address corrections | 9/11/2023 | TSE MING HUANG |
| Plan Check Approved | 10/11/2023 | TSE MING HUANG |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 5/15/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 5/18/2025 | DEROLD HAUFF |
| CofO Issued | 5/18/2025 | DEROLD HAUFF |
| Permit Finaled | 5/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/10/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/10/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 8/18/2023 | TOMMY YIN |
| Address approval | Cleared | 8/21/2023 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | JOSEPH RHYU |
| Roof/Waste drainage to street | Cleared | 8/21/2023 | JOSEPH RHYU |
| Sewer availability | Cleared | 8/21/2023 | JOSEPH RHYU |
| Hydrant and Access approval | Cleared | 10/2/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| Sewer | 1/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/8/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | DAVID FEILER |
| Gas Test | 3/21/2024 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | DAVID FEILER |
| Wood Frame | 3/21/2024 | Partial Approval | DAVID FEILER |
| Insulation | 3/27/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/27/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/22/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/31/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 5/31/2024 | Approved | JOSH MEISTER |
| Final | 9/18/2024 | No Access for Inspection | WILLIAM SIERRA |
| Green Building Final | 9/18/2024 | No Access for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Service/Power Release | 9/18/2024 | No Access for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 9/18/2024 | No Access for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 9/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/7/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 5/7/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 5/7/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/14/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |