2840 E WABASH AVE 1-52 90033
Certificate Information: 2840 E WABASH AVE 1-52 90033
- Application / Permit
- 23010-10000-00748
- Plan Check / Job No.
- B23LA03089
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 4 STORY WITH ROOF DECK TYPE VA 52 UNITS (INCLUDING 40 LOW INCOME UNITS, 11 MODERATE INCOME UNIT, AND 1 MANAGER UNIT) APARTMENT, USING INCENTIVES PER 12.22.A.25 / AB 1763 / AB2345
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- Issued on 6/28/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | VU NGUYEN |
| Assigned to Zoning Architect | 2/23/2023 | FRANCIS AHN |
| Corrections Issued | 3/3/2023 | VU NGUYEN |
| Quality Review Completed | 3/3/2023 | EUGENE BARBEAU |
| Plan Check Approved | 4/26/2024 | VU NGUYEN |
| Issued | 6/28/2024 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/2/2023 | MAYELA VILLA |
| Frnt yard landscape/Water mgmt | Cleared | 5/2/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 5/2/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 5/2/2023 | MAYELA VILLA |
| Opn space landscape/Water mgmt | Cleared | 5/2/2023 | MAYELA VILLA |
| Address approval | Cleared | 5/15/2023 | WALLIE JONG |
| Bicycle Parking | Cleared | 5/16/2023 | KATHERINE MENDOZA |
| Hydrant and Access approval | Cleared | 7/10/2023 | LAVEON RIDER |
| Highway dedication | Cleared | 8/2/2023 | WALLIE JONG |
| Building over 36-ft | Cleared | 8/22/2023 | CALOSHA APPROVED |
| Density Bonus | Cleared | 9/18/2023 | RICHARD TRUONG |
| SB8 RUD | Cleared | 9/18/2023 | RICHARD TRUONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | WALLIE JONG |
| Fire Marshal Fire Life Safety | Cleared | 11/22/2023 | MENOA AGHAJANI |
| Permit | Cleared | 11/28/2023 | WALLIE JONG |
| Trees in Parkway | Cleared | 12/5/2023 | ADALBERTO VERA |
| Sewer availability | Cleared | 12/7/2023 | AMBER CAMPBELL |
| DAS Clearance | Cleared | 12/21/2023 | ELIZABETH TOMS |
| Low Impact Development (LID) | Cleared | 3/6/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/7/2024 | WALLIE JONG |
| Green Code | Cleared | 3/11/2024 | VU NGUYEN |
| Miscellaneous | Cleared | 3/20/2024 | FRANCIS AHN |
| GPI Written Notices | Cleared | 4/24/2024 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 4/24/2024 | VU NGUYEN |
Contact Information
| Contractor | Ad Builders; Lic. No.: 1068899-B | , |
| Contractor | Allstate Drywall Inc; Lic. No.: 1068899-B | , |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 9/20/2024 | Approved | RAFAEL CORTES |
| Pre-Inspection | 10/9/2024 | Partial Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 1/2/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 1/6/2025 | Partial Approval | NICK DANERI |
| Footing/Foundation/Slab | 1/16/2025 | Conditional Approval | RONALD JIMENEZ |
| Pre-Inspection | 2/21/2025 | Corrections Issued | RAFAEL CORTES |
| Pre-Inspection | 2/25/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 2/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 2/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 2/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 2/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 3/3/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | No Access for Inspection | RAFAEL CORTES |
| Green Building Rough | 4/18/2025 | No Access for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 4/18/2025 | No Access for Inspection | RAFAEL CORTES |
| Wood Frame | 4/18/2025 | No Access for Inspection | RAFAEL CORTES |
| Drywall Nailing | 5/2/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 5/2/2025 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 5/22/2025 | Approved | RAFAEL CORTES |
| Pre-Inspection | 6/12/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Insulation | 6/18/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 6/18/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 7/17/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 7/17/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 7/31/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 7/31/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 8/1/2025 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 8/1/2025 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 8/6/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 8/6/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 8/11/2025 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 8/11/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 8/12/2025 | Partial Inspection | RONALD JIMENEZ |
| Wood Frame | 8/12/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 8/26/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 8/26/2025 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 9/4/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 9/11/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 9/22/2025 | Partial Approval | LARRY ARNICK |
| Insulation | 9/25/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 9/25/2025 | Approved | RAFAEL CORTES |
| Insulation | 10/2/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 10/2/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 10/6/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 10/8/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 10/8/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 10/14/2025 | No Access for Inspection | RAFAEL CORTES |
| Green Building Rough | 10/14/2025 | No Access for Inspection | RAFAEL CORTES |
| Insulation | 10/14/2025 | No Access for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 10/14/2025 | No Access for Inspection | RAFAEL CORTES |
| Wood Frame | 10/14/2025 | No Access for Inspection | RAFAEL CORTES |
| Drywall Nailing | 10/16/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 10/20/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 10/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 10/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 10/28/2025 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 10/28/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 11/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 11/3/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 11/3/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 11/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 11/5/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 11/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 11/10/2025 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 11/10/2025 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 11/10/2025 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 11/12/2025 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 11/12/2025 | Partial Approval | SCOTT SOBEL |
| Drywall Nailing | 11/17/2025 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 12/2/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 12/2/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 12/12/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 12/12/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 12/16/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 12/16/2025 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/22/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/24/2025 | No Access for Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 12/30/2025 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 1/7/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/7/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 1/7/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 1/7/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/14/2026 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 1/15/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/30/2026 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/30/2026 | Not Ready for Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 1/30/2026 | Approved | RONALD JIMENEZ |
| Insulation | 2/24/2026 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 3/6/2026 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 4/1/2026 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 4/7/2026 | Corrections Issued | RAFAEL CORTES |
| Drywall Nailing | 4/9/2026 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 4/9/2026 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 4/9/2026 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 5/7/2026 | Partial Approval | RAFAEL CORTES |