2840 E WABASH AVE 1-52 90033

Certificate Information: 2840 E WABASH AVE 1-52 90033

Application / Permit
23010-10000-00748
Plan Check / Job No.
B23LA03089
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY WITH ROOF DECK TYPE VA 52 UNITS (INCLUDING 40 LOW INCOME UNITS, 11 MODERATE INCOME UNIT, AND 1 MANAGER UNIT) APARTMENT, USING INCENTIVES PER 12.22.A.25 / AB 1763 / AB2345
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
Issued on 6/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/22/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 VU NGUYEN
Assigned to Zoning Architect 2/23/2023 FRANCIS AHN
Corrections Issued 3/3/2023 VU NGUYEN
Quality Review Completed 3/3/2023 EUGENE BARBEAU
Plan Check Approved 4/26/2024 VU NGUYEN
Issued 6/28/2024 APPLICANT

Permit Application Clearance Information

Clean Up Green Up Cleared 5/2/2023 MAYELA VILLA
Frnt yard landscape/Water mgmt Cleared 5/2/2023 MAYELA VILLA
Miscellaneous Cleared 5/2/2023 MAYELA VILLA
Miscellaneous Cleared 5/2/2023 MAYELA VILLA
Opn space landscape/Water mgmt Cleared 5/2/2023 MAYELA VILLA
Address approval Cleared 5/15/2023 WALLIE JONG
Bicycle Parking Cleared 5/16/2023 KATHERINE MENDOZA
Hydrant and Access approval Cleared 7/10/2023 LAVEON RIDER
Highway dedication Cleared 8/2/2023 WALLIE JONG
Building over 36-ft Cleared 8/22/2023 CALOSHA APPROVED
Density Bonus Cleared 9/18/2023 RICHARD TRUONG
SB8 RUD Cleared 9/18/2023 RICHARD TRUONG
Eng Process Fee Ord 176,300 Cleared 10/10/2023 WALLIE JONG
Fire Marshal Fire Life Safety Cleared 11/22/2023 MENOA AGHAJANI
Permit Cleared 11/28/2023 WALLIE JONG
Trees in Parkway Cleared 12/5/2023 ADALBERTO VERA
Sewer availability Cleared 12/7/2023 AMBER CAMPBELL
DAS Clearance Cleared 12/21/2023 ELIZABETH TOMS
Low Impact Development (LID) Cleared 3/6/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/7/2024 WALLIE JONG
Green Code Cleared 3/11/2024 VU NGUYEN
Miscellaneous Cleared 3/20/2024 FRANCIS AHN
GPI Written Notices Cleared 4/24/2024 VU NGUYEN
Grading Pre-Inspection Cleared 4/24/2024 VU NGUYEN

Contact Information

Contractor Ad Builders; Lic. No.: 1068899-B       ,
Contractor Allstate Drywall Inc; Lic. No.: 1068899-B       ,
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2024 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 9/20/2024 Approved RAFAEL CORTES
Pre-Inspection 10/9/2024 Partial Inspection RAFAEL CORTES
Footing/Foundation/Slab 1/2/2025 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 1/6/2025 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/16/2025 Conditional Approval RONALD JIMENEZ
Pre-Inspection 2/21/2025 Corrections Issued RAFAEL CORTES
Pre-Inspection 2/25/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 2/28/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 2/28/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 2/28/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 2/28/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 3/3/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 No Access for Inspection RAFAEL CORTES
Green Building Rough 4/18/2025 No Access for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 4/18/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 4/18/2025 No Access for Inspection RAFAEL CORTES
Drywall Nailing 5/2/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 5/2/2025 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 5/22/2025 Approved RAFAEL CORTES
Pre-Inspection 6/12/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 6/18/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 6/18/2025 Partial Approval RAFAEL CORTES
Insulation 7/17/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 7/17/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 7/31/2025 Approved RONALD JIMENEZ
Wood Frame 7/31/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/1/2025 Not Ready for Inspection LARRY ARNICK
Insulation 8/1/2025 Not Ready for Inspection LARRY ARNICK
Insulation 8/6/2025 Partial Approval RAFAEL CORTES
Wood Frame 8/6/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 8/11/2025 Partial Approval RONALD JIMENEZ
Wood Frame 8/11/2025 Partial Approval RONALD JIMENEZ
Insulation 8/12/2025 Partial Inspection RONALD JIMENEZ
Wood Frame 8/12/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/26/2025 Partial Approval RONALD JIMENEZ
Insulation 8/26/2025 Partial Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 9/4/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 9/11/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval RONALD JIMENEZ
Insulation 9/22/2025 Partial Approval LARRY ARNICK
Insulation 9/25/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 9/25/2025 Approved RAFAEL CORTES
Insulation 10/2/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 10/2/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 10/6/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 10/8/2025 Partial Approval RAFAEL CORTES
Insulation 10/8/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 10/14/2025 No Access for Inspection RAFAEL CORTES
Green Building Rough 10/14/2025 No Access for Inspection RAFAEL CORTES
Insulation 10/14/2025 No Access for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 10/14/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 10/14/2025 No Access for Inspection RAFAEL CORTES
Drywall Nailing 10/16/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 10/20/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 10/20/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 10/20/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 10/20/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 10/20/2025 Partial Approval RAFAEL CORTES
Insulation 10/24/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 10/24/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 10/28/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 10/28/2025 Approved RONALD JIMENEZ
Drywall Nailing 11/3/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 11/3/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 11/3/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 11/5/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 11/5/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 11/5/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 11/10/2025 Partial Approval EDWIN GREGORYONA
Insulation 11/10/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/10/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/12/2025 Partial Approval RONALD JIMENEZ
Special/Order Compliance 11/12/2025 Partial Approval SCOTT SOBEL
Drywall Nailing 11/17/2025 Partial Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Approved RONALD JIMENEZ
Drywall Nailing 12/2/2025 Partial Approval RAFAEL CORTES
Insulation 12/2/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 12/12/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 12/12/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 12/16/2025 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 12/16/2025 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 12/22/2025 Not Ready for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 12/24/2025 No Access for Inspection RAFAEL ESPINOZA
Drywall Nailing 12/30/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/7/2026 Partial Approval RAFAEL CORTES
Insulation 1/7/2026 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 1/7/2026 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 1/7/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 1/14/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/15/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 1/30/2026 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 1/30/2026 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 1/30/2026 Approved RONALD JIMENEZ
Insulation 2/24/2026 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 3/6/2026 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 4/1/2026 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/7/2026 Corrections Issued RAFAEL CORTES
Drywall Nailing 4/9/2026 Partial Approval RONALD JIMENEZ
Pre-Inspection 4/9/2026 Approved RONALD JIMENEZ
Special/Order Compliance 4/9/2026 Approved RONALD JIMENEZ
Pre-Inspection 5/7/2026 Partial Approval RAFAEL CORTES