850 1/2 N ROME DR 90065
Certificate Information: 850 1/2 N ROME DR 90065
- Application / Permit
- 23010-10000-00721
- Plan Check / Job No.
- B23LA02958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT (920 SF) PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | DANIEL YIP |
| Corrections Issued | 3/1/2023 | DANIEL YIP |
| Quality Review Completed | 3/3/2023 | KEN GILL |
| Building Plans Picked Up | 3/8/2023 | APPLICANT |
| Applicant returned to address corrections | 5/4/2023 | DANIEL YIP |
| Plan Check Approved | 5/8/2023 | DANIEL YIP |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 1/17/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/18/2025 | DEROLD HAUFF |
| CofO Issued | 1/18/2025 | DEROLD HAUFF |
| Permit Finaled | 1/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/9/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2023 | AMAAN MALIK |
| GPI Written Notices | Cleared | 3/10/2023 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 3/10/2023 | DANIEL YIP |
| Specific Plan | Cleared | 3/23/2023 | NASHYA JENSEN |
Contact Information
| Architect | Taalman,, Linda Evelyn; Lic. No.: C30187 | 2902 ROWENA AVENUE LOS ANGELES, CA 90039 |
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/31/2023 | Conditional Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 9/7/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/11/2023 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 9/11/2023 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/14/2023 | Conditional Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/17/2023 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/2/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/2/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/26/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/26/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/2/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/2/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/5/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/5/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/5/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/5/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 4/22/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 4/29/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/24/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/24/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/22/2024 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 11/22/2024 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/22/2024 | Partial Approval | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/22/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 12/12/2024 | Approved | OSVALDO PARAMO |
| Final | 12/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/12/2024 | Approved | OSVALDO PARAMO |
| Service/Power Release | 12/12/2024 | Approved | OSVALDO PARAMO |
| Final | 1/17/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |