2707 1/2-3/4 N BENEDICT ST 90039
Certificate Information: 2707 1/2-3/4 N BENEDICT ST 90039
- Application / Permit
- 23010-10000-00720
- Plan Check / Job No.
- B23LA02957
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 2-STORY ADUs (2-UNIT) PER CA 65852.2(e)(1)(D) AND APPLICABLE PARTS OF LAMC 12.22A.33(c)-(d), (g). NFPA 13D SOLAR INSTALLATION OF 2.38 KW EACH UNIT (4.76 KW TOTAL) PER TITLE 24 PRIOR TO C OF O.
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | VIVIAN LAO |
| Corrections Issued | 3/11/2023 | VIVIAN LAO |
| Quality Review Completed | 3/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/15/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 7/5/2023 | VIVIAN LAO |
| Plan Check Approved | 7/26/2023 | VIVIAN LAO |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 5/28/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
| CofO Issued | 5/28/2026 | DEROLD HAUFF |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/17/2023 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 3/22/2023 | MICHAEL SOTO |
| Low Impact Development (LID) | Cleared | 4/3/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/4/2023 | CINDY QI |
| ZI | Cleared | 5/12/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/16/2024 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 10/25/2024 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Sewer | 3/25/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/25/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 4/3/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/3/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 4/9/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 4/9/2026 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 4/9/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/27/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 4/27/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 4/27/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 4/27/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 4/27/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/27/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 4/29/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/29/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 5/14/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 5/14/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 5/14/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/21/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/21/2026 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 5/21/2026 | Not Required | HAMIK HARTOUNIAN |
| Final | 5/27/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |