735 N CURSON AVE 90046
Certificate Information: 735 N CURSON AVE 90046
- Application / Permit
- 23010-10000-00681
- Plan Check / Job No.
- B22LA26958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SFD WITH HAB. BASEMENT AND ATTACHED 2-CAR GARAGE. NFPA 13D
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Current Status
- Issued on 11/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | VIVIAN LAO |
| Corrections Issued | 3/15/2023 | VIVIAN LAO |
| Quality Review Completed | 3/15/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/22/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 9/15/2023 | VIVIAN LAO |
| Plan Check Approved | 10/26/2023 | VIVIAN LAO |
| Issued | 11/20/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2023 | ANA SORIANO |
| Permit | Cleared | 5/19/2023 | ANA SORIANO |
| Hydrant and Access approval | Cleared | 5/20/2023 | KURT CORRAL |
| Sewer availability | Cleared | 5/27/2023 | ANA SORIANO |
| Disturb/Remove Protected Trees | Cleared | 5/30/2023 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2023 | ANA SORIANO |
| Trees in Parkway | Cleared | 6/10/2023 | RICHARD SANCHEZ |
| SB8 RUD | Cleared | 6/26/2023 | KE ZHANG |
| Low Impact Development (LID) | Cleared | 8/25/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/31/2023 | ANA SORIANO |
Contact Information
| Contractor | Lg E&C; Lic. No.: 1036448-B | , |
| Contractor | Loengreen Inc; Lic. No.: 1036448-B | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Grading Pre-Inspection | 3/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Piling/Pier/Caisson | 3/19/2024 | Partial Inspection | AMIR NAZARIAN |
| Piling/Pier/Caisson | 3/28/2024 | Corrections Issued | AMIR NAZARIAN |
| Piling/Pier/Caisson | 4/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Piling/Pier/Caisson | 4/3/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Piling/Pier/Caisson | 4/5/2024 | Conditional Approval | AMIR NAZARIAN |
| Deputy Reinf. Concrete | 4/8/2024 | Partial Approval | AMIR NAZARIAN |
| Deputy Reinf. Concrete | 4/9/2024 | Partial Approval | AMIR NAZARIAN |
| Piling/Pier/Caisson | 4/9/2024 | Partial Approval | AMIR NAZARIAN |
| Deputy Reinf. Concrete | 4/10/2024 | Partial Approval | AMIR NAZARIAN |
| Piling/Pier/Caisson | 4/30/2024 | Partial Approval | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/14/2024 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 6/15/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 6/15/2024 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 6/16/2024 | Off-Hour Fees Due | |
| METHANE-Barrier | 6/17/2024 | Partial Inspection | AMIR NAZARIAN |
| METHANE-Subgrade | 6/17/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/25/2024 | Partial Approval | AMIR NAZARIAN |
| METHANE-Barrier | 6/25/2024 | Approved | AMIR NAZARIAN |
| METHANE-Subgrade | 6/25/2024 | Approved | AMIR NAZARIAN |
| Underground Mechanical | 6/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Underground Mechanical | 6/27/2024 | Partial Approval | AMIR NAZARIAN |
| Reinforced Concrete Frame | 7/16/2024 | Approved | AMIR NAZARIAN |
| Reinforced Concrete Frame | 7/17/2024 | Partial Approval | AMIR NAZARIAN |
| Deputy Shotcrete | 7/22/2024 | Approved | AMIR NAZARIAN |
| Deputy Shotcrete | 7/26/2024 | No Access for Inspection | AMIR NAZARIAN |
| Deputy Steel/Welding | 8/21/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/6/2024 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 9/24/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 10/1/2024 | Partial Approval | JOSE MACIAS |
| Structural Steel Frame | 10/10/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Steel/Welding | 10/11/2024 | Approved | JOSE MACIAS |
| Sewer | 11/5/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Other (see comments) | 11/20/2024 | Conditional Approval | JOSE MACIAS |
| Structural Steel Frame | 11/25/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Approved | JOSE MACIAS |
| Wood Frame | 1/2/2025 | Not Ready for Inspection | JOSE MACIAS |
| Wood Frame | 1/7/2025 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 1/27/2025 | Conditional Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 2/3/2025 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 3/18/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/17/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/17/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 5/7/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/7/2025 | Corrections Issued | JOSE MACIAS |
| Shower Pan | 5/7/2025 | Approved | JOSE MACIAS |
| Wood Frame | 5/14/2025 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/23/2025 | Not Ready for Inspection | JOSE MACIAS |
| Sewer | 5/23/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 5/23/2025 | Approved | JOSE MACIAS |
| Shower Pan | 5/30/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 5/30/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/9/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | JOSE MACIAS |
| Deck | 6/12/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 6/12/2025 | Approved | JOSE MACIAS |
| METHANE-Rough | 6/12/2025 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 6/12/2025 | Approved | JOSE MACIAS |
| Insulation | 6/30/2025 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 7/24/2025 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 7/29/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/16/2025 | Approved | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Partial Approval | JOSH MEISTER |
| Masonry Wall/Backfill | 1/30/2026 | Approved | JOSH MEISTER |
| Grading Pre-Inspection | 3/20/2026 | Not Ready for Inspection | JOSH MEISTER |