14951 W GREENLEAF ST 91403
Certificate Information: 14951 W GREENLEAF ST 91403
- Application / Permit
- 23010-10000-00672
- Plan Check / Job No.
- B23LA02778
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 20'-0" X 24'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - PER ENGINEER
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 2/26/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 9/20/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/9/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/9/2024 | ISIS ARGUETA |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 2/12/2025 | JACK KARGODORIAN |
| CofO in Progress | 3/8/2025 | JUAN VALENZUELA |
| No Progress | 3/10/2025 | JACK KARGODORIAN |
| CofO in Progress | 3/10/2025 | JACK KARGODORIAN |
| CofO in Progress | 4/4/2026 | RAUL OLAGI |
| CofO Issued | 4/9/2026 | RUBEN SALAS |
| Permit Finaled | 4/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/25/2023 | DANIEL ABRAMYAN |
| Address approval | Cleared | 3/3/2023 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 3/15/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 1/5/2024 | ROGELIO CORTES |
| Miscellaneous | Cleared | 1/9/2024 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gupta,, Raghu; Lic. No.: C87913 | 6024 BUCKINGHAM PKWY UNIT 16 CULVER CITY, CA 90230 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/1/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 3/4/2024 | Conditional Approval | DAVID MATSON |
| Deputy Other (see comments) | 4/17/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/2/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 8/2/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 8/2/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 8/5/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/21/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/21/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/21/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 8/21/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/28/2024 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 8/28/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 9/3/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/3/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 9/3/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/13/2024 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 12/13/2024 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/13/2024 | Approved | JACK KARGODORIAN |
| Green Building Final | 12/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 12/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 12/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 12/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 12/13/2024 | Approved | JACK KARGODORIAN |
| Structural Steel Frame | 12/13/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | JACK KARGODORIAN |
| Final | 1/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 1/28/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 1/28/2025 | Not Required | JACK KARGODORIAN |
| Final | 2/4/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 2/11/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/10/2025 | Corrections Issued | JACK KARGODORIAN |
| Order to Comply | 2/25/2026 | Not Required | JACK KARGODORIAN |
| Final | 4/4/2026 | OK to Issue CofO | RAUL OLAGI |