11885 W FOOTHILL BLVD 91342

Certificate Information: 11885 W FOOTHILL BLVD 91342

Application / Permit
23010-10000-00670
Plan Check / Job No.
B23LA02771
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Car Wash
Work Description
CONSTRUCT NEW CARWASH BUILDING CONSISTING OF TUNNEL, EQUIPMENT ROOM, & OFFICE (INCLUDING RESTROOM & CLEAN ROOM), VENDING MACHINE ENCLOSURE.
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
Issued on 3/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 JOE VO
Corrections Issued 3/9/2023 JOE VO
Quality Review Completed 3/10/2023 KEN GILL
Building Plans Picked Up 3/13/2023 APPLICANT
Green Plans Picked Up 3/22/2023 APPLICANT
Disabled Access Plans Picked Up 4/14/2023 APPLICANT
Applicant returned to address corrections 9/26/2023 JOE VO
Plan Check Approved 11/5/2024 JOE VO
Issued 3/13/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/8/2023 JOE VO
Drive Through Cleared 4/18/2023 MIGUEL CRISOSTOMO
Driveway location Cleared 4/18/2023 MIGUEL CRISOSTOMO
Eng Process Fee Ord 176,300 Cleared 4/22/2023 CARLOS AGUILERA
Sewer availability Cleared 5/4/2023 CARLOS AGUILERA
Trees in Parkway Cleared 6/6/2023 ADALBERTO VERA
ZA Case Cleared 6/8/2023 JAZMIN ROQUE
Hydrant and Access approval Cleared 6/28/2023 LAVEON RIDER
Highway dedication Cleared 10/14/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 7/17/2024 LUIS LUVANO
Permit Cleared 7/19/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/19/2024 CARLOS AGUILERA
Green Code Cleared 8/14/2024 JOE VO
DAS Clearance Cleared 8/29/2024 JOE VO
"Q" conditions Cleared 10/16/2024 DALIA MOKAYED
"T" removal Cleared 10/16/2024 DALIA MOKAYED
Automotive Use Cleared 10/16/2024 DALIA MOKAYED
Automotive Use Cleared 10/16/2024 DALIA MOKAYED
Automotive Use Cleared 10/16/2024 DALIA MOKAYED
Clean Up Green Up Cleared 10/16/2024 DALIA MOKAYED
Comm Cor/Mini-Mall Cleared 10/16/2024 DALIA MOKAYED
Comm Cor/Mini-Mall Cleared 10/16/2024 DALIA MOKAYED
Comm Cor/Mini-Mall Cleared 10/16/2024 DALIA MOKAYED
ZA Case Cleared 10/16/2024 DALIA MOKAYED

Contact Information

Architect Paszterko,, Andrew Elemer; Lic. No.: C12253 2055 N ALVARADO ST      LOS ANGELES, CA 90039
Contractor Thomas Charles E Company Inc; Lic. No.: 302015-B 13701 ALMA AVENUE      GARDENA, CA 90249
Engineer St, Jacques, Michael Patrick; Lic. No.: C66815 11684 HOLMES AVE      JURUPA VALLEY, CA 91752

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/14/2025 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 7/30/2025 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 7/31/2025 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 8/7/2025 No Access for Inspection RAFAEL CORTES
Footing/Foundation/Slab 8/7/2025 Partial Approval KENNETH ROBERTS
Footing/Foundation/Slab 8/13/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 8/20/2025 Corrections Issued ANDREW DORSO
Special/Order Compliance 8/21/2025 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 9/9/2025 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 10/1/2025 Not Ready for Inspection GREGORY POMISH
Masonry Wall/Backfill 10/2/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 10/6/2025 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 10/15/2025 Partial Inspection GREGORY POMISH
Deputy Reinf. Masonry 10/17/2025 No Result Entered DANNY RODRIGUEZ
Masonry Wall/Backfill 10/17/2025 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Masonry 10/20/2025 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 10/20/2025 Corrections Issued JOHN KITCKO
Deputy Reinf. Masonry 10/22/2025 Approved JOHN KITCKO
Masonry Wall/Backfill 10/22/2025 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 10/23/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/3/2025 Approved JOHN KITCKO
Reinforced Masonry Frame 11/3/2025 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Masonry 11/4/2025 No Result Entered DANNY RODRIGUEZ
Masonry Wall/Backfill 11/5/2025 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 11/6/2025 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 11/7/2025 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 11/7/2025 Partial Approval ANDREW DORSO
Deputy Reinf. Masonry 11/12/2025 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 11/12/2025 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 11/13/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/10/2025 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Partial Approval GREGORY POMISH
Insulation 12/23/2025 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 12/23/2025 Partial Approval GREGORY POMISH
Drywall Nailing 1/14/2026 Approved JOHN KITCKO