11885 W FOOTHILL BLVD 91342
Certificate Information: 11885 W FOOTHILL BLVD 91342
- Application / Permit
- 23010-10000-00670
- Plan Check / Job No.
- B23LA02771
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (9) Car Wash
- Work Description
- CONSTRUCT NEW CARWASH BUILDING CONSISTING OF TUNNEL, EQUIPMENT ROOM, & OFFICE (INCLUDING RESTROOM & CLEAN ROOM), VENDING MACHINE ENCLOSURE.
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- Issued on 3/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | JOE VO |
| Corrections Issued | 3/9/2023 | JOE VO |
| Quality Review Completed | 3/10/2023 | KEN GILL |
| Building Plans Picked Up | 3/13/2023 | APPLICANT |
| Green Plans Picked Up | 3/22/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 4/14/2023 | APPLICANT |
| Applicant returned to address corrections | 9/26/2023 | JOE VO |
| Plan Check Approved | 11/5/2024 | JOE VO |
| Issued | 3/13/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/8/2023 | JOE VO |
| Drive Through | Cleared | 4/18/2023 | MIGUEL CRISOSTOMO |
| Driveway location | Cleared | 4/18/2023 | MIGUEL CRISOSTOMO |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/4/2023 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 6/6/2023 | ADALBERTO VERA |
| ZA Case | Cleared | 6/8/2023 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 6/28/2023 | LAVEON RIDER |
| Highway dedication | Cleared | 10/14/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/17/2024 | LUIS LUVANO |
| Permit | Cleared | 7/19/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/19/2024 | CARLOS AGUILERA |
| Green Code | Cleared | 8/14/2024 | JOE VO |
| DAS Clearance | Cleared | 8/29/2024 | JOE VO |
| "Q" conditions | Cleared | 10/16/2024 | DALIA MOKAYED |
| "T" removal | Cleared | 10/16/2024 | DALIA MOKAYED |
| Automotive Use | Cleared | 10/16/2024 | DALIA MOKAYED |
| Automotive Use | Cleared | 10/16/2024 | DALIA MOKAYED |
| Automotive Use | Cleared | 10/16/2024 | DALIA MOKAYED |
| Clean Up Green Up | Cleared | 10/16/2024 | DALIA MOKAYED |
| Comm Cor/Mini-Mall | Cleared | 10/16/2024 | DALIA MOKAYED |
| Comm Cor/Mini-Mall | Cleared | 10/16/2024 | DALIA MOKAYED |
| Comm Cor/Mini-Mall | Cleared | 10/16/2024 | DALIA MOKAYED |
| ZA Case | Cleared | 10/16/2024 | DALIA MOKAYED |
Contact Information
| Architect | Paszterko,, Andrew Elemer; Lic. No.: C12253 | 2055 N ALVARADO ST LOS ANGELES, CA 90039 |
| Contractor | Thomas Charles E Company Inc; Lic. No.: 302015-B | 13701 ALMA AVENUE GARDENA, CA 90249 |
| Engineer | St, Jacques, Michael Patrick; Lic. No.: C66815 | 11684 HOLMES AVE JURUPA VALLEY, CA 91752 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/14/2025 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 7/30/2025 | Not Ready for Inspection | GREGORY POMISH |
| Deputy Reinf. Concrete | 7/31/2025 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 8/7/2025 | No Access for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/7/2025 | Partial Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 8/13/2025 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 8/20/2025 | Corrections Issued | ANDREW DORSO |
| Special/Order Compliance | 8/21/2025 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/9/2025 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 10/1/2025 | Not Ready for Inspection | GREGORY POMISH |
| Masonry Wall/Backfill | 10/2/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 10/6/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 10/15/2025 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Masonry | 10/17/2025 | No Result Entered | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 10/17/2025 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/20/2025 | Conditional Approval | JEFFREY DURAN |
| Reinforced Masonry Frame | 10/20/2025 | Corrections Issued | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/22/2025 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 10/22/2025 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/23/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 11/3/2025 | Approved | JOHN KITCKO |
| Reinforced Masonry Frame | 11/3/2025 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/4/2025 | No Result Entered | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 11/5/2025 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/6/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/7/2025 | Conditional Approval | JEFFREY DURAN |
| Reinforced Masonry Frame | 11/7/2025 | Partial Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 11/12/2025 | Conditional Approval | JEFFREY DURAN |
| Reinforced Concrete Frame | 11/12/2025 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/13/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 12/10/2025 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 12/23/2025 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 12/23/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 1/14/2026 | Approved | JOHN KITCKO |