6650 E FERRARA ST 90042

Certificate Information: 6650 E FERRARA ST 90042

Application / Permit
23010-10000-00651
Plan Check / Job No.
B23LA02689
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 6/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 MICHAEL LOPEZ
Corrections Issued 3/10/2023 MICHAEL LOPEZ
Quality Review Completed 3/17/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/21/2023 APPLICANT
Applicant returned to address corrections 4/13/2023 MICHAEL LOPEZ
Applicant returned to address corrections 5/22/2023 JAD BASMA
Plan Check Approved 6/1/2023 JAD BASMA
Plan Check Approved 6/1/2023 JAD BASMA
Issued 6/5/2023 APPLICANT
CofO in Progress 3/5/2024 ALIZAH MAYAGOITIA
CofO in Progress 3/6/2024 ALIZAH MAYAGOITIA
Permit Finaled 3/8/2024 DEROLD HAUFF
CofO Issued 3/8/2024 DEROLD HAUFF
Permit Finaled 3/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/26/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/26/2023 JEANIE LAM
Sewer availability Cleared 4/26/2023 JEANIE LAM
Low Impact Development (LID) Cleared 5/10/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/11/2023 TREVOR QUAN
GPI Written Notices Cleared 6/1/2023 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 6/1/2023 MICHAEL LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Howe,, Carl William; Lic. No.: C44773 4358 SEPULVEDA BLVD      CULVER CITY, CA 90230

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2023 Approved AMY COLIN
Pre-Inspection 6/12/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval AMY COLIN
Green Building Rough 6/28/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 6/28/2023 Partial Approval AMY COLIN
PLUMBING-Rough 6/29/2023 Partial Approval AMY COLIN
Rough-Elec/Plmb/HVAC 6/29/2023 Partial Approval AMY COLIN
Insulation 7/6/2023 Partial Approval AMY COLIN
PLUMBING-Rough 7/6/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval RUBEN SALAS
PLUMBING-Rough 8/11/2023 Approved AMY COLIN
Sewer 8/11/2023 Approved AMY COLIN
ELECTRICAL-Rough 8/15/2023 Partial Approval AMY COLIN
Underground Mechanical 8/15/2023 Partial Approval AMY COLIN
PLUMBING-Rough 8/23/2023 Partial Approval BRENDAN MORELLI
Underground Mechanical 8/23/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 9/15/2023 Approved AMY COLIN
ELECTRICAL-Rough 9/15/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Approved AMY COLIN
Green Building Rough 9/15/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 9/15/2023 Approved AMY COLIN
MERV13>=Rough 9/15/2023 Approved AMY COLIN
PLUMBING-Rough 9/15/2023 Approved AMY COLIN
Service/Power Release 9/15/2023 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 9/15/2023 Approved AMY COLIN
Interior/Exterior Lathing 9/20/2023 Partial Approval AMY COLIN
Green Building Rough 9/29/2023 Approved ROY SPAULDING
Insulation 9/29/2023 Approved ROY SPAULDING
Drywall Nailing 10/13/2023 Approved ROY SPAULDING
Shower Pan 10/26/2023 Approved ROY SPAULDING
ELECTRICAL-Final 12/7/2023 Not Ready for Inspection ROY SPAULDING
HVAC-Final 12/7/2023 Approved ROY SPAULDING
Service/Power Release 12/7/2023 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 12/7/2023 Approved ROY SPAULDING
ELECTRICAL-Final 12/18/2023 Approved ROY SPAULDING
HVAC-Final 12/18/2023 Approved ROY SPAULDING
Final 2/26/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/26/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 2/26/2024 Approved ALIZAH MAYAGOITIA
MERV13>=Final 2/26/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/26/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 2/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 3/4/2024 OK to Issue CofO ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 3/4/2024 Approved ALIZAH MAYAGOITIA
Final 3/5/2024 OK to Issue CofO ALIZAH MAYAGOITIA