4033 N GUARDIA AVE 90032

Certificate Information: 4033 N GUARDIA AVE 90032

Application / Permit
23010-10000-00648
Plan Check / Job No.
B23LA02659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan - NEW SFD NO COVERED PARKING REQUIREMENT PER AB2097
Permit Issued
Issued on 7/3/2024
Issuing Office
Current Status
CofO Issued on 5/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 SUNMIN LEE
Corrections Issued 3/30/2023 SUNMIN LEE
Quality Review Completed 4/4/2023 GARO TELMI
Applicant returned to address corrections 5/21/2024 SUNMIN LEE
Applicant returned to address corrections 6/14/2024 SUNMIN LEE
Plan Check Approved 6/21/2024 SUNMIN LEE
Plan Check Approved 7/2/2024 SUNMIN LEE
Issued 7/3/2024 APPLICANT
CofO in Progress 5/9/2025 LILIANA PORTILLO
Permit Finaled 5/11/2025 DEROLD HAUFF
CofO Issued 5/11/2025 DEROLD HAUFF
Permit Finaled 5/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/10/2023 JEANIE LAM
Low Impact Development (LID) Cleared 3/28/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/29/2024 JESSICA OPINION
Sewer availability Cleared 4/9/2024 CHRISTINA BRACO
Grading Pre-Inspection Cleared 5/9/2024 SUNMIN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/10/2024 Corrections Issued JOHN QUINTANILLA
Pre-Inspection 9/13/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 9/30/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/30/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/30/2024 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 10/3/2024 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 10/3/2024 Conditional Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 10/8/2024 Partial Approval LILIANA PORTILLO
Insulation 10/8/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/15/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 11/15/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Approved LILIANA PORTILLO
Gas Test 11/15/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 11/15/2024 Corrections Issued LILIANA PORTILLO
Sewer 11/15/2024 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 11/15/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 12/23/2024 Approved BRENDAN MORELLI
Gas Test 12/23/2024 Approved BRENDAN MORELLI
HVAC-Rough 12/23/2024 Approved BRENDAN MORELLI
Insulation 12/23/2024 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 12/23/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 12/23/2024 Conditional Approval BRENDAN MORELLI
Sewer 12/23/2024 Approved BRENDAN MORELLI
Underground Mechanical 12/23/2024 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 12/31/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 12/31/2024 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/31/2024 Approved ALIZAH MAYAGOITIA
Wood Frame 12/31/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 1/3/2025 Corrections Issued ANTHONY RAMOS
Shower Pan 1/3/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 1/7/2025 Approved BRENDAN MORELLI
Drywall Nailing 1/7/2025 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Approved BRENDAN MORELLI
Insulation 1/7/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/7/2025 Approved BRENDAN MORELLI
Shower Pan 1/7/2025 Approved BRENDAN MORELLI
Gas Test 3/11/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/4/2025 Approved LILIANA PORTILLO
Final 4/4/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/4/2025 Approved LILIANA PORTILLO
Green Building Final 4/4/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 4/4/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 4/4/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 4/4/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 4/4/2025 Approved LILIANA PORTILLO
Final 5/8/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 5/8/2025 Approved LILIANA PORTILLO
HVAC-Final 5/8/2025 Approved LILIANA PORTILLO
Service/Power Release 5/8/2025 Approved LILIANA PORTILLO
Verify Rec and Parks Fee Memo 5/8/2025 Approved LILIANA PORTILLO