3310 E ALICE ST 90065
Certificate Information: 3310 E ALICE ST 90065
- Application / Permit
- 23010-10000-00643
- Plan Check / Job No.
- B22LA26290
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ePlan NEW 2-CAR GARAGE
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/15/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/24/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/28/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 9/13/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/13/2023 | MAHNAZ NOURHASHEMI |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 8/23/2024 | OSVALDO PARAMO |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/21/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2023 | STEVE MELGAR |
| Stormwater Pollution Mitigatn | Cleared | 4/6/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 4/27/2023 | STEVE MELGAR |
| Supp. Use District POD/CDO/TDO | Cleared | 8/20/2023 | NATHAN ROMINE |
| GPI Written Notices | Cleared | 9/13/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Lapointe Brothers Inc; Lic. No.: 1037066-B | 2629 FOOTHILL BLVD SUITE 350 LA CRESCENTA, CA 91214 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/22/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/19/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 3/21/2024 | Conditional Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 4/11/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/12/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 4/12/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/18/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 5/21/2024 | Approved | OSVALDO PARAMO |
| Final | 7/22/2024 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 7/22/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 7/22/2024 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/22/2024 | Approved | OSVALDO PARAMO |
| Final | 8/22/2024 | OK to Issue CofO | OSVALDO PARAMO |