3939-3941 1/2 S HALLDALE AVE 90062
Certificate Information: 3939-3941 1/2 S HALLDALE AVE 90062
- Application / Permit
- 23010-10000-00603
- Plan Check / Job No.
- B23LA02379
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan***PROPOSED DUPLEX WITH ATTACHED GARAGE AND ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/21/2023
- Issuing Office
- Current Status
- CofO Issued on 4/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | SINA KHOSRAVI |
| Corrections Issued | 3/6/2023 | SINA KHOSRAVI |
| Quality Review Completed | 3/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/25/2023 | SINA KHOSRAVI |
| Plan Check Approved | 8/17/2023 | SINA KHOSRAVI |
| Issued | 8/21/2023 | APPLICANT |
| CofO in Progress | 4/18/2025 | SABAS ALONSO |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
| CofO Issued | 4/19/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/21/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 5/31/2023 | MATTHEW CRAIG |
| SB8 RUD | Cleared | 6/14/2023 | KE ZHANG |
| ZI | Cleared | 6/14/2023 | MAYELA VILLA |
| DAS Clearance | Cleared | 6/20/2023 | Ricardo Ramirez Solis |
| Low Impact Development (LID) | Cleared | 6/29/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/13/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/13/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 10/24/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 3/22/2024 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 4/3/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/22/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/22/2024 | Approved | SABAS ALONSO |
| Shower Pan | 5/22/2024 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 5/24/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/24/2024 | Approved | SABAS ALONSO |
| Wood Frame | 5/24/2024 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/31/2024 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 5/31/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/31/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| Drywall Nailing | 6/12/2024 | Conditional Approval | JOSE MACIAS |
| Interior/Exterior Lathing | 7/22/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Shower Pan | 7/22/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | ALEX COLIN |
| Shower Pan | 7/26/2024 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | SABAS ALONSO |
| Final | 4/4/2025 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 4/4/2025 | No Access for Inspection | SABAS ALONSO |
| Smoke Detectors | 4/4/2025 | No Access for Inspection | SABAS ALONSO |
| Special/Order Compliance | 4/4/2025 | Partial Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/4/2025 | Approved | SABAS ALONSO |
| Final | 4/11/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 4/11/2025 | Approved | SABAS ALONSO |
| Final | 4/15/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 4/15/2025 | Approved | SABAS ALONSO |