4170 S CENTRAL AVE 90011
Certificate Information: 4170 S CENTRAL AVE 90011
- Application / Permit
- 23010-10000-00549
- Plan Check / Job No.
- B23LA02124
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (9) Gasoline Station
- Work Description
- PROPOSED 1-STORY RETAIL STORE FOR NEW GASOLINE STATION PER ZA-2020-1518-CU. 1 OF 6
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | MICHAEL LOPEZ |
| Disabled Access Plans Picked Up | 3/9/2023 | APPLICANT |
| Corrections Issued | 3/16/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 3/24/2023 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 5/4/2023 | APPLICANT |
| Applicant returned to address corrections | 11/29/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/5/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/8/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/17/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 6/18/2025 | MICHAEL LOPEZ |
| Issued | 7/3/2025 | APPLICANT |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 5/18/2023 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 6/20/2023 | MICHAEL LOPEZ |
| Community Plan Implem. Overlay | Cleared | 6/22/2023 | MOHAMMAD HASAN |
| Driveway location | Cleared | 6/22/2023 | MOHAMMAD HASAN |
| Internal circulation | Cleared | 6/22/2023 | MOHAMMAD HASAN |
| Food Service Establishment | Cleared | 6/26/2023 | PAWAN VERMA |
| Encroachment in public way | Cleared | 6/28/2023 | KATHERINE MENDOZA |
| Supplemental Onsite WTS | Cleared | 7/3/2023 | KENNETH BROWNE |
| Community Plan Implem. Overlay | Cleared | 7/6/2023 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 7/6/2023 | ADALBERTO VERA |
| Address approval | Cleared | 7/12/2023 | CINDY QI |
| Sewer availability | Cleared | 7/31/2023 | CINDY QI |
| Underground fuel tank | Cleared | 7/31/2023 | FIRE DEPARTMENT |
| Community Plan Implem. Overlay | Cleared | 8/7/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 10/11/2023 | RIDWAN HARDY |
| Green Code | Cleared | 3/1/2024 | MICHAEL MARTINEZ |
| Highway dedication | Cleared | 6/25/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 7/8/2024 | ERNEST TSE |
| Gasoline station | Cleared | 7/12/2024 | SCAQMD APPROVED |
| Roof/Waste drainage to street | Cleared | 7/18/2024 | ARMEN MEHRABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | CELINA MORENO |
| Permit | Cleared | 7/31/2024 | ARMEN MEHRABIAN |
| "D" conditions | Cleared | 1/14/2025 | JASON CHAN |
| Comm Cor/Mini-Mall | Cleared | 1/14/2025 | JASON CHAN |
| ZA Case | Cleared | 1/14/2025 | JASON CHAN |
| Community Plan Implem. Overlay | Cleared | 4/8/2025 | ANACANY HURTADO |
| Redevelopment Project Area | Cleared | 4/9/2025 | ELIZABETH GALLARDO |
| Food establishment approval | Cleared | 5/8/2025 | LACDHS APPROVED |
Contact Information
| Architect | Paszterko,, Andrew Elemer; Lic. No.: C12253 | 2055 N ALVARADO ST LOS ANGELES, CA 90039 |
| Contractor | Chase Construction Inc; Lic. No.: 700816-B | 1825 PANDORA AVE LOS ANGELES, CA 90025 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2025 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/7/2025 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | JAMES POWERS |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 10/30/2025 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 12/16/2025 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/17/2025 | Partial Approval | JAMES POWERS |
| Wood Frame | 12/17/2025 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 1/16/2026 | Partial Approval | JAMES POWERS |
| Green Building Rough | 4/22/2026 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 4/22/2026 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 4/22/2026 | Partial Approval | JAMES POWERS |