5001 N ODESSA AVE 91436
Certificate Information: 5001 N ODESSA AVE 91436
- Application / Permit
- 23010-10000-00521
- Plan Check / Job No.
- B23LA02018
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan New 2 Story (SFD) with attached garage
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Current Status
- CofO Issued on 8/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | JAD BASMA |
| Corrections Issued | 2/25/2023 | JAD BASMA |
| Quality Review Completed | 3/8/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/10/2023 | JAD BASMA |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 6/11/2024 | THOMAS FINNILA |
| Permit Finaled | 8/30/2024 | JOHN JANSON |
| CofO Issued | 8/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/20/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/25/2023 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2023 | MARKOS PEREZ-BRAN |
| Low Impact Development (LID) | Cleared | 4/5/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | MEGAN GODINEZ |
| Trees in Parkway | Cleared | 4/23/2023 | ADALBERTO VERA |
| Permit | Cleared | 4/24/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 6/12/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/14/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 7/18/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/11/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/11/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 8/11/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 8/18/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/24/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 8/24/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 8/24/2023 | Corrections Issued | SEAN HAUPT |
| Interior/Exterior Lathing | 8/24/2023 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 8/28/2023 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/29/2023 | Approved | VINCENT HANLEY |
| Insulation | 9/5/2023 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 9/13/2023 | Approved | VINCENT HANLEY |
| Gas Test | 12/11/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/7/2024 | Approved | VINCENT HANLEY |
| Final | 3/7/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/7/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/7/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 3/7/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/7/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/7/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/26/2024 | Approved | VINCENT HANLEY |
| Final | 4/12/2024 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/12/2024 | Approved | VINCENT HANLEY |
| Final | 5/16/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 5/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 6/10/2024 | OK to Issue CofO | THOMAS FINNILA |