14594 W LYLE ST 91342

Certificate Information: 14594 W LYLE ST 91342

Application / Permit
23010-10000-00508
Plan Check / Job No.
B23LA01950
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1200 SQFT 2-STORY ADU AT REAR OF LOT. PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 2/9/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2023 APPLICANT
Assigned to Plan Check Engineer 2/15/2023 DANIEL SANJUAN
Corrections Issued 2/15/2023 DANIEL SANJUAN
Building Plans Picked Up 2/16/2023 APPLICANT
Applicant returned to address corrections 9/8/2023 WEIJIAN HUANG
Plan Check Approved 9/12/2023 JOSEPH RAFOLS
Issued 2/9/2024 APPLICANT
CofO in Progress 5/7/2025 KEVIN BERBERYAN
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 6/20/2023 RIDWAN HARDY
Construction within easement Cleared 6/20/2023 RIDWAN HARDY
Address approval Cleared 6/21/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/26/2023 LEE GUILBEAUX
Sewer availability Cleared 6/26/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/17/2023 MATTHEW CRAIG
Stormwater Pollution Mitigatn Cleared 9/5/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/9/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2024 Partial Inspection KEVIN BERBERYAN
Sewer 5/1/2024 Approved KEVIN BERBERYAN
Underground Mechanical 5/1/2024 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/15/2024 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/20/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 5/20/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 7/8/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 7/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 7/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Deputy Wood Construction 7/9/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 9/10/2024 Conditional Approval KEVIN BERBERYAN
Green Building Rough 9/10/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 9/10/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/10/2024 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 9/18/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/18/2024 Approved KEVIN BERBERYAN
Insulation 9/19/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/19/2024 Approved KEVIN BERBERYAN
Drywall Nailing 10/1/2024 Approved KEVIN BERBERYAN
Green Building Rough 10/1/2024 Approved KEVIN BERBERYAN
Service/Power Release 3/6/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 3/17/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/17/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 3/17/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 3/17/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 3/17/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 3/17/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 3/17/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 3/21/2025 Approved KEVIN BERBERYAN
Final 3/21/2025 Partial Inspection KEVIN BERBERYAN
Green Building Final 3/21/2025 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 3/21/2025 Approved KEVIN BERBERYAN
Smoke Detectors 3/21/2025 Approved KEVIN BERBERYAN
Final 5/5/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 5/5/2025 Approved KEVIN BERBERYAN