14594 W LYLE ST 91342
Certificate Information: 14594 W LYLE ST 91342
- Application / Permit
- 23010-10000-00508
- Plan Check / Job No.
- B23LA01950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1200 SQFT 2-STORY ADU AT REAR OF LOT. PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2023 | DANIEL SANJUAN |
| Corrections Issued | 2/15/2023 | DANIEL SANJUAN |
| Building Plans Picked Up | 2/16/2023 | APPLICANT |
| Applicant returned to address corrections | 9/8/2023 | WEIJIAN HUANG |
| Plan Check Approved | 9/12/2023 | JOSEPH RAFOLS |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 5/7/2025 | KEVIN BERBERYAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/20/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/20/2023 | RIDWAN HARDY |
| Address approval | Cleared | 6/21/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/26/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/17/2023 | MATTHEW CRAIG |
| Stormwater Pollution Mitigatn | Cleared | 9/5/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/9/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2024 | Partial Inspection | KEVIN BERBERYAN |
| Sewer | 5/1/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 5/1/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/20/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/8/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 7/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 7/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Deputy Wood Construction | 7/9/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 9/10/2024 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 9/10/2024 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 9/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/18/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/18/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 9/19/2024 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 9/19/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/1/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/1/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 3/6/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 3/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 3/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 3/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 3/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 3/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/21/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/21/2025 | Partial Inspection | KEVIN BERBERYAN |
| Green Building Final | 3/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 3/21/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 3/21/2025 | Approved | KEVIN BERBERYAN |
| Final | 5/5/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 5/5/2025 | Approved | KEVIN BERBERYAN |