729 1/2 E 56TH ST 90011
Certificate Information: 729 1/2 E 56TH ST 90011
- Application / Permit
- 23010-10000-00371
- Plan Check / Job No.
- B23LA01556
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story detached ADU per GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). Framing to comply with WFPP.
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/4/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/17/2023 | APPLICANT |
| Applicant returned to address corrections | 3/21/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 5/31/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 6/6/2023 | ZAW HAN |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 12/16/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/21/2023 | DEROLD HAUFF |
| CofO Issued | 12/21/2023 | DEROLD HAUFF |
| Permit Finaled | 12/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 3/14/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/14/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/21/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 6/6/2023 | MARCO SANCHEZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 7/7/2023 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/13/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 8/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 8/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 9/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 10/19/2023 | Conditional Approval | BRENDAN MORELLI |
| Underground Mechanical | 10/19/2023 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 10/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/2/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/15/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |