2653 S VETERAN AVE 90064

Certificate Information: 2653 S VETERAN AVE 90064

Application / Permit
23010-10000-00353
Plan Check / Job No.
B23LA01433
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) STATE APPROVED FBH 722 SQFT DETACHED ADU
Permit Issued
Issued on 10/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 RACHEL BEYENE
Corrections Issued 2/2/2023 RACHEL BEYENE
Building Plans Picked Up 2/3/2023 APPLICANT
Plan Check Approved 10/23/2023 JOSEPH RAFOLS
Issued 10/23/2023 APPLICANT
CofO in Progress 4/9/2024 JESUS PINEDA
Permit Finaled 4/12/2024 DANIEL ORRANTE
CofO Issued 4/12/2024 DANIEL ORRANTE
Permit Finaled 4/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/9/2023 RAYMOND MUGAMBWA
Specific Plan Cleared 2/21/2023 KYLE WINSTON
Eng Process Fee Ord 176,300 Cleared 2/23/2023 RAYMOND MUGAMBWA
Sewer availability Cleared 2/23/2023 RAYMOND MUGAMBWA
Grading Pre-Inspection Cleared 2/28/2023 BRIAN MILLER
Hydrant and Access approval Cleared 3/7/2023 KURT CORRAL
Stormwater Pollution Mitigatn Cleared 3/17/2023 MELINEH AGHAKHABIAN
Specific Plan Cleared 4/4/2023 EDUARDO HERMOSO
Roof/Waste drainage to street Cleared 4/5/2023 AHMED AMARRAGY
Construction near power lines Cleared 7/11/2023 TINA MIRANDA

Contact Information

Contractor Cover Building Technologies; Lic. No.: 1039029-B 1415 W 178TH ST      GARDENA, CA 90248
Engineer Nielsen,, Gregory Michael Wat; Lic. No.: S6653 4991 WESTPARK DR      NORTH HOLLYWOOD, CA 91601

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2023 Conditional Approval HERBERT GIRON
Underground Mechanical 1/29/2024 Partial Approval JESUS PINEDA
Underground Mechanical 2/3/2024 Partial Approval KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Ready JESUS PINEDA
BUILDING-Rough-Frame 3/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 3/6/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 3/6/2024 Approved KEVIN SARGSYAN
MERV13>=Final 3/6/2024 Approved KEVIN SARGSYAN
MERV13>=Rough 3/6/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/6/2024 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 3/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 3/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 3/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 3/14/2024 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/20/2024 Partial Approval JESUS PINEDA
Final 3/20/2024 Not Ready for Inspection JESUS PINEDA
Service/Power Release 3/20/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 3/20/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 3/20/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/9/2024 Approved JESUS PINEDA
Final 4/9/2024 OK to Issue CofO JESUS PINEDA
Service/Power Release 4/9/2024 Approved JESUS PINEDA