3635 S GREENWOOD AVE 90066

Certificate Information: 3635 S GREENWOOD AVE 90066

Application / Permit
23010-10000-00351
Plan Check / Job No.
B23LA01423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU IN THE REAR OF (E) SFD PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/3/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/1/2023 WEIJIAN HUANG
Corrections Issued 2/1/2023 WEIJIAN HUANG
Building Plans Picked Up 2/10/2023 APPLICANT
Plan Check Approved 3/3/2023 ADAM HEGAZI
Issued 3/3/2023 APPLICANT
CofO in Progress 12/5/2023 JESUS RODRIGUEZ
Permit Finaled 12/7/2023 DANIEL ORRANTE
CofO Issued 12/7/2023 DANIEL ORRANTE
Permit Finaled 12/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Stormwater Pollution Mitigatn Cleared 2/21/2023 ERNEST TSE
Address approval Cleared 2/22/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/24/2023 DINAH GARIN
Sewer availability Cleared 2/24/2023 DINAH GARIN
Specific Plan Cleared 2/28/2023 FREDDY GARCIA
Grading Pre-Inspection Cleared 3/1/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 3/3/2023 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2023 Approved JESUS RODRIGUEZ
Sewer 4/4/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 4/10/2023 Conditional Approval HERBERT GIRON
Deputy Reinf. Concrete 4/12/2023 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 5/8/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 5/8/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 5/8/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/12/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 5/12/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/12/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/19/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/19/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/19/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 5/19/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 6/2/2023 Approved JESUS RODRIGUEZ
Insulation 6/2/2023 Approved JESUS RODRIGUEZ
Shower Pan 6/5/2023 Approved EVAN COOPER
Drywall Nailing 6/21/2023 Approved EVAN COOPER
Interior/Exterior Lathing 6/21/2023 Approved EVAN COOPER
ELECTRICAL-Final 10/16/2023 Approved JESUS RODRIGUEZ
Gas Test 10/16/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/16/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved JESUS RODRIGUEZ
HVAC-Final 10/23/2023 Corrections Issued JESUS RODRIGUEZ
Final 11/2/2023 Not Ready for Inspection HERBERT GIRON
Green Building Final 11/2/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Final 11/2/2023 Not Ready for Inspection HERBERT GIRON
Service/Power Release 11/2/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 11/2/2023 Approved HERBERT GIRON
Final 11/6/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/6/2023 Approved JESUS RODRIGUEZ
HVAC-Final 11/6/2023 Approved JESUS RODRIGUEZ
Service/Power Release 11/6/2023 Approved JESUS RODRIGUEZ
Final 12/4/2023 OK to Issue CofO JESUS RODRIGUEZ