1328 W 68TH ST 90044

Certificate Information: 1328 W 68TH ST 90044

Application / Permit
23010-10000-00347
Plan Check / Job No.
B23LA01391
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT PER State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)“The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 10/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/1/2023 GEORGE ALVAREZ
Corrections Issued 2/1/2023 GEORGE ALVAREZ
Building Plans Picked Up 2/17/2023 APPLICANT
Applicant returned to address corrections 3/20/2023 WEIJIAN HUANG
Plan Check Approved 3/21/2023 DANIEL SANJUAN
Issued 3/21/2023 APPLICANT
CofO in Progress 9/28/2023 ENRIQUE MIRELES
CofO in Progress 9/28/2023 ENRIQUE MIRELES
Permit Finaled 10/3/2023 DEROLD HAUFF
CofO Issued 10/3/2023 DEROLD HAUFF
Permit Finaled 10/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/8/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/8/2023 ADRIAN SANCHEZ
Sewer availability Cleared 3/8/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 3/20/2023 ADRIAN SANCHEZ

Contact Information

Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/20/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/28/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/1/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/6/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 6/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 6/6/2023 Approved ENRIQUE MIRELES
HVAC-Rough 6/6/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 6/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 6/6/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Approved ENRIQUE MIRELES
HVAC-Rough 6/12/2023 No Access for Inspection ENRIQUE MIRELES
PLUMBING-Rough 6/12/2023 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 6/21/2023 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 6/21/2023 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 6/21/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 6/21/2023 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 6/29/2023 Partial Approval ENRIQUE MIRELES
Insulation 7/7/2023 Approved ENRIQUE MIRELES
Drywall Nailing 7/13/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/17/2023 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 9/8/2023 Approved ENRIQUE MIRELES
Final 9/8/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/8/2023 Approved ENRIQUE MIRELES
Green Building Final 9/8/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/8/2023 Approved ENRIQUE MIRELES
Final 9/21/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 9/21/2023 Not Ready for Inspection STUART CHAPMAN
Final 9/26/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 9/26/2023 Approved ENRIQUE MIRELES