9623 S HAAS AVE 90047

Certificate Information: 9623 S HAAS AVE 90047

Application / Permit
23010-10000-00341
Plan Check / Job No.
B23LA01372
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ( 32'-11" X 22'-11" ) DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/9/2023
Issuing Office
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 ROSENDO MEDINA
Corrections Issued 2/7/2023 ROSENDO MEDINA
Applicant returned to address corrections 7/18/2023 MADISON ODELL
Plan Check Approved 8/4/2023 MADISON ODELL
Issued 10/9/2023 APPLICANT
CofO in Progress 11/12/2024 AMIR NAZARIAN
Permit Finaled 11/21/2024 DEROLD HAUFF
Permit Finaled 11/21/2024 DEROLD HAUFF
CofO Issued 11/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/7/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/21/2023 ADRIAN SANCHEZ
Sewer availability Cleared 7/21/2023 ADRIAN SANCHEZ
Stormwater Pollution Mitigatn Cleared 7/25/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 8/2/2023 ADRIAN SANCHEZ

Contact Information

Architect Baek,, Sunpil; Lic. No.: NA35323       ,
Contractor Sunway Construction Inc; Lic. No.: 697180-B       ,
Engineer Hwang,, Junho; Lic. No.: NA5592       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/29/2023 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 12/29/2023 Corrections Issued ENRIQUE MIRELES
METHANE-Barrier 12/29/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 12/29/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 1/4/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/4/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/23/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/29/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Approved JOSE MACIAS
Deputy Wood Construction 4/3/2024 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Approved JOSE MACIAS
HVAC-Rough 5/14/2024 Approved JOSE MACIAS
PLUMBING-Rough 5/14/2024 Approved JOSE MACIAS
Wood Frame 5/14/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 5/24/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 6/7/2024 Conditional Approval JOSE MACIAS
Green Building Rough 6/7/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 6/7/2024 Approved JOSE MACIAS
METHANE-Rough 6/7/2024 Approved JOSE MACIAS
Shower Pan 6/7/2024 Corrections Issued JOSE MACIAS
Verify Sprinkler Sign Off 6/7/2024 Approved JOSE MACIAS
Shower Pan 6/12/2024 Approved JOSE MACIAS
Insulation 6/18/2024 Approved JOSE MACIAS
Drywall Nailing 6/25/2024 Approved JOSE MACIAS
PLUMBING-Final 8/30/2024 Approved JOSE MACIAS
Sewer 8/30/2024 Approved JOSE MACIAS
Underground Mechanical 8/30/2024 Approved JOSE MACIAS
ELECTRICAL-Final 10/16/2024 Corrections Issued AMIR NAZARIAN
Final 10/16/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 10/16/2024 Corrections Issued AMIR NAZARIAN
Service/Power Release 10/16/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Final 10/21/2024 Approved JOSE MACIAS
Final 10/21/2024 Corrections Issued JOSE MACIAS
HVAC-Final 10/21/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 10/29/2024 Approved JOSE MACIAS
Final 10/29/2024 Conditional Approval JOSE MACIAS
Green Building Final 10/29/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved JOSE MACIAS
Service/Power Release 10/29/2024 Approved JOSE MACIAS
Smoke Detectors 10/29/2024 Approved JOSE MACIAS
Final 11/8/2024 OK to Issue CofO AMIR NAZARIAN