1360 N LAUREL WAY 90210
Certificate Information: 1360 N LAUREL WAY 90210
- Application / Permit
- 23010-10000-00331
- Plan Check / Job No.
- B23LA01335
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | DANIEL YIP |
| Corrections Issued | 2/22/2023 | DANIEL YIP |
| Quality Review Completed | 2/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/21/2023 | DANIEL YIP |
| Plan Check Approved | 5/25/2023 | DANIEL YIP |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 5/21/2026 | CARLOS MATAMOROS |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | DINAH GARIN |
| Permit | Cleared | 3/9/2023 | DINAH GARIN |
| Sewer availability | Cleared | 3/9/2023 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 3/24/2023 | MATTHEW CRAIG |
| Stormwater Pollution Mitigatn | Cleared | 5/2/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/3/2023 | ANTHONY MAINEZ |
| Building over 36-ft | Cleared | 5/25/2023 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/25/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/25/2023 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 5/25/2023 | DANIEL YIP |
| Miscellaneous | Cleared | 5/25/2023 | DANIEL YIP |
| Miscellaneous | Cleared | 5/25/2023 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2023 | Partial Inspection | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 8/23/2023 | Approved | BRENDAN LOONEY |
| Piling/Pier/Caisson | 8/23/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Other (see comments) | 8/25/2023 | Conditional Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 8/31/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/13/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 9/14/2023 | Approved | BRENDAN LOONEY |
| Piling/Pier/Caisson | 9/14/2023 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 9/14/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/27/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 10/3/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 11/3/2023 | Approved | BRENDAN LOONEY |
| Piling/Pier/Caisson | 11/3/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 11/7/2023 | Conditional Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 11/16/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/20/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 11/22/2023 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 11/30/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 12/1/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 12/15/2023 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/15/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 12/26/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 1/16/2024 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 1/23/2024 | Conditional Approval | BRENDAN LOONEY |
| Pool Piping | 2/28/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 3/4/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/5/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Gunite | 3/13/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/18/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 3/21/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 3/28/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/28/2024 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 3/29/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/2/2024 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 4/23/2024 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 5/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/10/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Partial Approval | SEAN HAUPT |
| Light Gage Steel Frame | 5/10/2024 | Partial Approval | SEAN HAUPT |
| Structural Steel Frame | 5/10/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 5/14/2024 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 5/22/2024 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 5/23/2024 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 5/24/2024 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 5/29/2024 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 5/30/2024 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 5/30/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 5/31/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 6/25/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | SEAN HAUPT |
| Structural Steel Frame | 7/29/2024 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 8/1/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Drilled-In Anchors | 8/29/2024 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 8/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 11/14/2024 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 1/15/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/28/2025 | Partial Approval | SEAN HAUPT |
| Shower Pan | 1/28/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 1/29/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 2/3/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 2/5/2025 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/10/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 2/20/2025 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/21/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 2/24/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 3/11/2025 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 3/12/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | SEAN HAUPT |
| Green Building Rough | 3/26/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/26/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 4/11/2025 | Partial Approval | SEAN HAUPT |
| Shower Pan | 4/11/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/16/2025 | Approved | SEAN HAUPT |
| Insulation | 4/18/2025 | Approved | SEAN HAUPT |
| Drywall Nailing | 5/1/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 8/13/2025 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Approved | SEAN HAUPT |
| Pool Piping | 9/22/2025 | Approved | SEAN HAUPT |
| Underground Mechanical | 10/7/2025 | Partial Approval | SEAN HAUPT |
| Service/Power Release | 11/24/2025 | Approved | SEAN HAUPT |
| HVAC-Final | 12/3/2025 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 1/7/2026 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/20/2026 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/26/2026 | Approved | CARLOS MATAMOROS |
| Gas Test | 1/26/2026 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/26/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/27/2026 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 2/4/2026 | Approved | CARLOS MATAMOROS |
| Final | 5/11/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 5/11/2026 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/11/2026 | Corrections Issued | CARLOS MATAMOROS |
| Final | 5/21/2026 | OK to Issue CofO | CARLOS MATAMOROS |
| Smoke Detectors | 5/21/2026 | Approved | CARLOS MATAMOROS |