1535 W 80TH ST 90047

Certificate Information: 1535 W 80TH ST 90047

Application / Permit
23010-10000-00322
Plan Check / Job No.
B23LA01265
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY 20'8" X 33'2" ACCESSORY DWELLING UNIT AND (N) LAUNDRY (42.65 SF) WITHIN PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEERING.
Permit Issued
Issued on 5/30/2023
Issuing Office
Current Status
CofO Issued on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 MOHAMMAD ESMAILI
Corrections Issued 2/4/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 4/28/2023 MADISON ODELL
Plan Check Approved 5/12/2023 MADISON ODELL
Issued 5/30/2023 APPLICANT
CofO in Progress 5/8/2024 MICHAEL LEWIS
CofO in Progress 5/8/2024 MICHAEL LEWIS
CofO in Progress 5/16/2024 MICHAEL LEWIS
Permit Finaled 6/3/2024 DEROLD HAUFF
CofO Issued 6/3/2024 DEROLD HAUFF
Permit Finaled 6/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/21/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/23/2023 CELINA MORENO
Sewer availability Cleared 2/23/2023 CELINA MORENO
Stormwater Pollution Mitigatn Cleared 3/21/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/24/2023 CELINA MORENO
Construction near power lines Cleared 3/31/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/19/2023 Not Ready for Inspection MICHAEL LEWIS
Sewer 7/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 7/19/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 7/31/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 7/31/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 9/7/2023 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 10/4/2023 Approved MICHAEL LEWIS
HVAC-Rough 10/4/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/4/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/6/2023 Corrections Issued STUART CHAPMAN
Green Building Rough 10/6/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/6/2023 Approved STUART CHAPMAN
Wood Frame 10/6/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/13/2023 Approved MICHAEL LEWIS
Green Building Rough 10/13/2023 Approved MICHAEL LEWIS
Insulation 10/13/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/13/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/20/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/31/2023 Approved MICHAEL LEWIS
Gas Test 11/22/2023 Not Ready for Inspection RONNIE MINDANAO
HVAC-Final 11/22/2023 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Final 11/22/2023 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 11/22/2023 Not Ready for Inspection RONNIE MINDANAO
Gas Test 11/29/2023 Approved MICHAEL LEWIS
PLUMBING-Final 11/29/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved MICHAEL LEWIS
Shower Pan 11/29/2023 Approved MICHAEL LEWIS
Underground Mechanical 11/29/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/16/2024 Corrections Issued DAVID FEILER
Final 2/16/2024 Corrections Issued DAVID FEILER
Green Building Final 2/16/2024 Corrections Issued DAVID FEILER
HVAC-Final 2/16/2024 Corrections Issued DAVID FEILER
PLUMBING-Final 2/16/2024 Corrections Issued DAVID FEILER
Service/Power Release 2/16/2024 Not Ready for Inspection DAVID FEILER
Smoke Detectors 2/16/2024 Corrections Issued DAVID FEILER
ELECTRICAL-Final 4/9/2024 Corrections Issued MICHAEL LEWIS
Final 4/9/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 4/9/2024 Partial Inspection MICHAEL LEWIS
HVAC-Final 4/9/2024 Partial Inspection MICHAEL LEWIS
PLUMBING-Final 4/9/2024 Approved MICHAEL LEWIS
Service/Power Release 4/9/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 4/9/2024 Approved MICHAEL LEWIS
Final 4/16/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 4/16/2024 Approved MICHAEL LEWIS
Final 5/7/2024 Partial Approval MICHAEL LEWIS
Service/Power Release 5/7/2024 Approved MICHAEL LEWIS
Special/Order Compliance 5/8/2024 Corrections Issued MICHAEL LEWIS
Final 5/15/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 5/15/2024 Approved MICHAEL LEWIS