8880 W EVANVIEW DR 90069

Certificate Information: 8880 W EVANVIEW DR 90069

Application / Permit
23010-10000-00318
Plan Check / Job No.
B23LA01226
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan New 2 story single family dwelling w/ basement and attached garage "COMPLY WITH DEPARTMENT ORDER effective date 05/03/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
Issued on 9/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/26/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 JAD BASMA
Corrections Issued 2/18/2023 JAD BASMA
Quality Review Completed 3/2/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/21/2023 JAD BASMA
Applicant returned to address corrections 5/10/2023 JAD BASMA
Applicant returned to address corrections 7/16/2023 JAD BASMA
Applicant returned to address corrections 7/20/2023 JAD BASMA
Plan Check Approved 8/8/2023 JAD BASMA
Plan Check Approved 8/15/2023 JAD BASMA
Plan Check Approved 8/18/2023 JAD BASMA
No Progress 8/18/2023 JAD BASMA
Plan Check Approved 8/18/2023 JAD BASMA
Plan Check Approved 9/15/2023 JAD BASMA
No Progress 9/18/2023 JAD BASMA
Plan Check Approved 9/18/2023 JAD BASMA
Issued 9/19/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/10/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 3/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 3/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 3/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 3/21/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/21/2023 TREVOR QUAN
Permit Cleared 3/21/2023 TREVOR QUAN
Sewer availability Cleared 3/21/2023 TREVOR QUAN
Street Frontage Cleared 3/21/2023 TREVOR QUAN
Miscellaneous Cleared 3/28/2023 ALBERT TAM
Excavation more than 5-ft deep Cleared 4/12/2023 CALOSHA APPROVED
BHO/Hillside ordinance Cleared 5/2/2023 CELINA MORENO
Trees in Parkway Cleared 5/2/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 5/16/2023 RUEL COLE
Roof/Waste drainage to street Cleared 6/9/2023 ADRIAN SANCHEZ
Stormwater Pollution Mitigatn Cleared 6/9/2023 LUIS LUVANO
Building over 36-ft Cleared 7/19/2023 CALOSHA APPROVED
GPI Written Notices Cleared 7/19/2023 JAD BASMA
Grading Pre-Inspection Cleared 7/19/2023 JAD BASMA

Contact Information

Architect Sun,, David Hao Chen; Lic. No.: NA19374       ,
Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: NA72413       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/31/2024 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 6/4/2024 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 6/11/2024 Conditional Approval RICHARD DOCKUS
Deputy Reinf. Concrete 6/17/2024 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/18/2024 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 6/24/2024 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/19/2024 Partial Approval RAUL BARAJAS
Special/Order Compliance 7/19/2024 Corrections Issued RAUL BARAJAS
Deputy Reinf. Concrete 8/7/2024 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 8/9/2024 Partial Approval RAUL BARAJAS
Pre-Inspection 11/19/2024 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/6/2024 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/6/2024 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/17/2024 Partial Approval ROY SPAULDING
Special/Order Compliance 12/17/2024 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 1/23/2025 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 2/3/2025 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 2/3/2025 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 3/4/2025 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 3/4/2025 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 3/25/2025 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 4/11/2025 Partial Inspection RAUL BARAJAS
Reinforced Concrete Frame 4/11/2025 Partial Approval RAUL BARAJAS
Special/Order Compliance 4/14/2025 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 6/11/2025 Partial Approval SCOTT FINNILA
Underground Mechanical 6/30/2025 Not Ready for Inspection BRENDAN MORELLI
Piling/Pier/Caisson 7/9/2025 Corrections Issued BRENDAN MORELLI
Piling/Pier/Caisson 9/22/2025 Partial Approval ROY SPAULDING
Deputy Reinf. Concrete 9/29/2025 Conditional Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 12/16/2025 Conditional Approval BRIAN SULLIVAN
Deputy Other (see comments) 12/16/2025 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/18/2025 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 12/18/2025 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 1/16/2026 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 1/16/2026 Partial Approval DAVID WILLIAMS
PLUMBING-Rough 2/11/2026 Partial Approval DAVID WILLIAMS
Underground Mechanical 2/11/2026 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 2/26/2026 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 3/2/2026 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 3/13/2026 Partial Approval DAVID WILLIAMS
Deputy Other (see comments) 4/9/2026 Conditional Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 4/10/2026 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 4/10/2026 Partial Approval DAVID WILLIAMS
Deputy Other (see comments) 5/12/2026 Conditional Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 5/13/2026 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 6/2/2026 Partial Approval BRENDAN MORELLI
Special/Order Compliance 6/2/2026 Corrections Issued BRENDAN MORELLI