13730 W CHANDLER BLVD 91401

Certificate Information: 13730 W CHANDLER BLVD 91401

Application / Permit
23010-10000-00284
Plan Check / Job No.
B23LA01043
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 800 S.F. ACCESSORY DWELLING UNIT AT REAR OF THE LOT PER WFPP (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 FERNANDO FLORES
Corrections Issued 2/2/2023 FERNANDO FLORES
Applicant returned to address corrections 5/24/2023 JOSEPH RAFOLS
Plan Check Approved 5/25/2023 AUNG SOE
Issued 5/25/2023 APPLICANT
CofO in Progress 3/4/2024 DAVID ANDERSON
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/2/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 3/7/2023 RYAN KIM
Sewer availability Cleared 3/7/2023 RYAN KIM
Hydrant and Access approval Cleared 4/7/2023 RUEL COLE
Stormwater Pollution Mitigatn Cleared 5/24/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 5/25/2023 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/31/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 6/6/2023 Approved RYAN SALAZAR
Pre-Inspection 6/30/2023 Partial Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 8/24/2023 Approved RYAN SALAZAR
HVAC-Rough 8/24/2023 Approved RYAN SALAZAR
PLUMBING-Rough 8/24/2023 Approved RYAN SALAZAR
Insulation 9/6/2023 Approved RYAN SALAZAR
Shower Pan 9/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/14/2023 Partial Approval RYAN SALAZAR
Sewer 9/14/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/26/2024 Approved CHRISTOPHER ROJAS
Final 2/26/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 2/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 2/26/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 2/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 2/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/26/2024 Approved CHRISTOPHER ROJAS
Final 3/1/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 3/1/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved DAVID ANDERSON
Service/Power Release 3/1/2024 Approved DAVID ANDERSON
Smoke Detectors 3/1/2024 Approved DAVID ANDERSON