410 S BUNDY DR 90049
Certificate Information: 410 S BUNDY DR 90049
- Application / Permit
- 23010-10000-00254
- Plan Check / Job No.
- B23LA00920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ACCESSORY DWELLING UNIT PER R LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 4/4/2023
- Issuing Office
- Current Status
- CofO in Progress on 6/24/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/4/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/8/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/31/2023 | ALEC MOUSAKHANIAN |
| Issued | 4/4/2023 | APPLICANT |
| CofO in Progress | 6/21/2024 | ARAM AVEDISIAN |
| No Progress | 6/24/2024 | KENNETH NAGLE |
| CofO in Progress | 6/24/2024 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 2/23/2023 | JOSHUA JONES |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/27/2023 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 3/27/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/27/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 3/28/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | DINAH GARIN |
Contact Information
| Architect | Cardenas,, Joshua A; Lic. No.: C34620 | 26701 MCBREAN PARKWAY STE 170 SANTA CLARITA, CA 91355 |
| Contractor | Boulder Builders Inc; Lic. No.: 915981-B | , |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2023 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/9/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/12/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/7/2023 | Partial Approval | CARLOS MATAMOROS |
| Sewer | 7/7/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/17/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/23/2023 | Corrections Issued | KEVIN SARGSYAN |
| Drywall Nailing | 8/23/2023 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 9/14/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Shower Pan | 9/14/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/19/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/20/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 9/20/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/22/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/28/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 10/2/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/5/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/5/2023 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 11/15/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 11/16/2023 | Approved | KEVIN SARGSYAN |
| Final | 3/12/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/12/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 3/12/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Service/Power Release | 3/12/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Smoke Detectors | 3/12/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/13/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 6/13/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 6/13/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/13/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Required | STEPHANIE SWANSON |
| Service/Power Release | 6/13/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/21/2024 | Approved | ARAM AVEDISIAN |
| Final | 6/21/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 6/21/2024 | Approved | ARAM AVEDISIAN |
| Final | 9/23/2024 | Corrections Issued | ARAM AVEDISIAN |