18139 W HARTLAND ST 91335
Certificate Information: 18139 W HARTLAND ST 91335
- Application / Permit
- 23010-10000-00193
- Plan Check / Job No.
- B23LA00824
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2023 | FERNANDO FLORES |
| Corrections Issued | 1/31/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/24/2023 | DANIEL YIP |
| Plan Check Approved | 9/12/2023 | SHANGQIN XIE |
| Issued | 9/12/2023 | APPLICANT |
| CofO in Progress | 6/11/2024 | JEFFREY BULL |
| Permit Finaled | 8/8/2024 | JOHN JANSON |
| CofO Issued | 8/8/2024 | JOHN JANSON |
| Permit Finaled | 8/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/8/2023 | CARLOS AGUILERA |
| ZI | Cleared | 3/16/2023 | BRENNEN OBETO |
| Construction near power lines | Cleared | 6/27/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/3/2023 | CARLOS AGUILERA |
| Stormwater Pollution Mitigatn | Cleared | 8/3/2023 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2023 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 10/30/2023 | Corrections Issued | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 12/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 12/19/2023 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | JEFFREY PARD |
| Green Building Rough | 12/28/2023 | Approved | JEFFREY PARD |
| Insulation | 1/11/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 1/11/2024 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 1/16/2024 | Approved | JOHN KIDWELL |
| Shower Pan | 2/2/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/7/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 2/22/2024 | Approved | HENRY KIM |
| Final | 5/23/2024 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 5/23/2024 | Approved | JEFFREY BULL |
| Green Building Final | 5/23/2024 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 5/23/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 5/23/2024 | Approved | JEFFREY BULL |
| Final | 6/10/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 6/10/2024 | Approved | JEFFREY BULL |
| Service/Power Release | 6/26/2024 | Approved | JEFFREY BULL |