1345 W 78TH ST 90044

Certificate Information: 1345 W 78TH ST 90044

Application / Permit
23010-10000-00165
Plan Check / Job No.
B23LA00637
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE-STORY ( 40'-6" X 22'-8" ) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 ROSENDO MEDINA
Corrections Issued 1/31/2023 ROSENDO MEDINA
Plan Check Approved 8/4/2023 MADISON ODELL
Issued 12/7/2023 APPLICANT
CofO in Progress 4/1/2025 JOHN QUINTANILLA
Permit Finaled 4/3/2025 DEROLD HAUFF
CofO Issued 4/3/2025 DEROLD HAUFF
Permit Finaled 4/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 6/9/2023 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 7/5/2023 ANTHONY VARGAS
Address approval Cleared 8/1/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/1/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 8/1/2023 CHRISTINA BRACO
Sewer availability Cleared 8/1/2023 CHRISTINA BRACO

Contact Information

Contractor Dreams Renovation Inc; Lic. No.: 1101893-B       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 2/12/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 3/4/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 3/6/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval MICHAEL LEWIS
Insulation 3/18/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Approved CRAIG DAVIS
PLUMBING-Rough 4/5/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 4/10/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 4/10/2024 Partial Approval MICHAEL LEWIS
HVAC-Rough 4/16/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 4/16/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 4/18/2024 Approved MICHAEL LEWIS
Green Building Rough 4/18/2024 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 4/18/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 4/24/2024 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 4/26/2024 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 5/2/2024 Approved DAVID FEILER
Green Building Rough 5/2/2024 Approved DAVID FEILER
Insulation 5/2/2024 Approved DAVID FEILER
Drywall Nailing 5/13/2024 Approved JOSH MEISTER
PLUMBING-Rough 5/31/2024 Partial Inspection MICHAEL LEWIS
Underground Mechanical 5/31/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 6/12/2024 Approved MICHAEL LEWIS
Shower Pan 6/12/2024 Approved MICHAEL LEWIS
Underground Mechanical 7/17/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 7/24/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 7/24/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 7/24/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 7/31/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 7/31/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 7/31/2024 Approved MICHAEL LEWIS
Sewer 7/31/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 9/3/2024 Approved CRAIG DAVIS
HVAC-Final 9/3/2024 Not Ready for Inspection CRAIG DAVIS
Final 9/19/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 9/19/2024 Approved MICHAEL LEWIS
Green Building Final 9/19/2024 Approved MICHAEL LEWIS
HVAC-Final 9/19/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/19/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 9/19/2024 Approved MICHAEL LEWIS
Smoke Detectors 9/19/2024 Approved MICHAEL LEWIS
Final 2/14/2025 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved JOHN QUINTANILLA
Final 3/26/2025 OK to Issue CofO JOHN QUINTANILLA
HVAC-Final 3/26/2025 Approved JOHN QUINTANILLA