1345 W 78TH ST 90044
Certificate Information: 1345 W 78TH ST 90044
- Application / Permit
- 23010-10000-00165
- Plan Check / Job No.
- B23LA00637
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE-STORY ( 40'-6" X 22'-8" ) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | ROSENDO MEDINA |
| Corrections Issued | 1/31/2023 | ROSENDO MEDINA |
| Plan Check Approved | 8/4/2023 | MADISON ODELL |
| Issued | 12/7/2023 | APPLICANT |
| CofO in Progress | 4/1/2025 | JOHN QUINTANILLA |
| Permit Finaled | 4/3/2025 | DEROLD HAUFF |
| CofO Issued | 4/3/2025 | DEROLD HAUFF |
| Permit Finaled | 4/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/9/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 7/5/2023 | ANTHONY VARGAS |
| Address approval | Cleared | 8/1/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 8/1/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/1/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Dreams Renovation Inc; Lic. No.: 1101893-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 2/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 3/4/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 3/6/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 3/18/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 4/5/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/10/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 4/16/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/16/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 4/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 4/18/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/24/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 4/26/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 5/2/2024 | Approved | DAVID FEILER |
| Green Building Rough | 5/2/2024 | Approved | DAVID FEILER |
| Insulation | 5/2/2024 | Approved | DAVID FEILER |
| Drywall Nailing | 5/13/2024 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 5/31/2024 | Partial Inspection | MICHAEL LEWIS |
| Underground Mechanical | 5/31/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/12/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 6/12/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/17/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/24/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/24/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 7/24/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/31/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/31/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 7/31/2024 | Approved | MICHAEL LEWIS |
| Sewer | 7/31/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/3/2024 | Approved | CRAIG DAVIS |
| HVAC-Final | 9/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 9/19/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/19/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 9/19/2024 | Approved | MICHAEL LEWIS |
| HVAC-Final | 9/19/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 9/19/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 9/19/2024 | Approved | MICHAEL LEWIS |
| Final | 2/14/2025 | Conditional Approval | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Final | 3/26/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| HVAC-Final | 3/26/2025 | Approved | JOHN QUINTANILLA |