1839 W MIDDLETON PL 90062
Certificate Information: 1839 W MIDDLETON PL 90062
- Application / Permit
- 23010-10000-00155
- Plan Check / Job No.
- B22LA26878
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1-story ADU 30'-0" x 30'-8". Type VA construction
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- Current Status
- Issued on 6/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | JOE VO |
| Corrections Issued | 2/10/2023 | JOE VO |
| Applicant returned to address corrections | 3/16/2023 | JOE VO |
| Plan Check Approved | 5/30/2023 | JOE VO |
| Issued | 6/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2023 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 4/17/2023 | KURT CORRAL |
| Stormwater Pollution Mitigatn | Cleared | 5/22/2023 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2023 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/27/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/27/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/18/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 10/18/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/18/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/14/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 1/30/2024 | No Access for Inspection | SABAS ALONSO |
| Pre-Inspection | 2/1/2024 | Partial Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 2/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 2/8/2024 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 2/8/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/8/2024 | Approved | SABAS ALONSO |
| Insulation | 2/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/29/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 3/1/2024 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 3/1/2024 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 3/1/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 3/14/2024 | Approved | JOSH MEISTER |
| Green Building Rough | 3/14/2024 | Approved | JOSH MEISTER |
| Shower Pan | 7/24/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 7/26/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/1/2024 | Approved | ALEX COLIN |