Piling/Pier/Caisson
|
4/29/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Piling/Pier/Caisson
|
4/30/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Piling/Pier/Caisson
|
5/1/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
6/6/2025
|
Approved
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2025
|
Corrections Issued
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
6/30/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Pre-Inspection
|
7/17/2025
|
Approved
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
8/4/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Deputy Methane Barrier
|
8/5/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
8/5/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Deputy Methane Barrier
|
8/6/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
8/26/2025
|
Partial Inspection
|
JEROME BLACKWOOD
|
|
Green Building Rough
|
9/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
METHANE-Rough
|
9/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
9/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
9/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
9/2/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
9/16/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
METHANE-Rough
|
9/16/2025
|
Approved
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
9/16/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
9/16/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/22/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Green Building Rough
|
10/6/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/6/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
10/6/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
10/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
10/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Green Building Rough
|
10/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Verify Sprinkler Sign Off
|
10/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
10/20/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
10/22/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/3/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
11/3/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
11/12/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
11/12/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
11/17/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
11/18/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
11/19/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
11/19/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
11/21/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/21/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
11/21/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/26/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/26/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
11/26/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
11/26/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
12/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
12/2/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
12/2/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
12/8/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
12/11/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Green Building Rough
|
12/11/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
12/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
12/11/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
12/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
12/12/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Green Building Rough
|
12/15/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/15/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
12/15/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/16/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
12/16/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/16/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
12/16/2025
|
Approved
|
EDWIN GREGORYONA
|
|
Insulation
|
12/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
12/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
12/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
12/18/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
12/18/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
12/18/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Structural Steel Frame
|
12/18/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
12/19/2025
|
No Access for Inspection
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
12/19/2025
|
No Access for Inspection
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
12/19/2025
|
No Access for Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
12/22/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
12/22/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
12/22/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Structural Steel Frame
|
12/22/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
12/23/2025
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
12/24/2025
|
No Access for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
12/31/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
12/31/2025
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
1/7/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
1/8/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Wood Frame
|
1/8/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
1/9/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
1/9/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Drywall Nailing
|
1/14/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
1/14/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Insulation
|
1/14/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
1/14/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
1/21/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
1/21/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
1/26/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Pre-Inspection
|
1/26/2026
|
Approved
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
1/29/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
1/30/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
3/10/2026
|
Corrections Issued
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
3/11/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
3/18/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
3/23/2026
|
Partial Approval
|
PAUL BAZERKANIAN
|
|
Special/Order Compliance
|
4/2/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
4/3/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Final
|
4/3/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
4/3/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Green Building Final
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
METHANE-Barrier
|
4/3/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
METHANE-Subgrade
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
SGSOV-Seismic Gas S/O Valve
|
4/3/2026
|
SGSOV Not Ready
|
RAFAEL CORTES
|
|
Smoke Detectors
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
4/3/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
5/7/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
METHANE-Barrier
|
5/7/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
METHANE-Subgrade
|
5/7/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
5/7/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Final
|
5/14/2026
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/14/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
5/14/2026
|
Corrections Issued
|
RAFAEL ESPINOZA
|