4231 N SAUGUS AVE 91403
Certificate Information: 4231 N SAUGUS AVE 91403
- Application / Permit
- 23010-10000-00073
- Plan Check / Job No.
- B22LA26840
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ATT 2 CAR GAR
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | CARLOS MONTES |
| Corrections Issued | 1/29/2023 | CARLOS MONTES |
| Quality Review Completed | 1/31/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/18/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 5/11/2023 | CARLOS MONTES |
| Plan Check Approved | 6/9/2023 | CARLOS MONTES |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 9/12/2024 | JACK KARGODORIAN |
| Permit Finaled | 9/25/2024 | DANIEL ORRANTE |
| CofO Issued | 9/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/1/2023 | CARLOS AGUILERA |
| Distance to fire station | Cleared | 2/22/2023 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 2/22/2023 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 2/27/2023 | ADALBERTO VERA |
| Stormwater Pollution Mitigatn | Cleared | 3/9/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/13/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/18/2023 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 4/18/2023 | CARLOS MONTES |
| Permit | Cleared | 5/20/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2023 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 7/14/2023 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 7/19/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 7/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/3/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/26/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/26/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/6/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 11/7/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 11/7/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/13/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 11/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 11/30/2023 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 11/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 12/5/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 12/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 12/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/15/2023 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 12/15/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 12/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 12/29/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 1/9/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 1/9/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Shower Pan | 1/11/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/17/2024 | Approved | CRAIG DAVIS |
| Underground Mechanical | 5/16/2024 | Approved | JACK KARGODORIAN |
| Gas Test | 6/12/2024 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 6/17/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/14/2024 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 8/14/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/14/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/4/2024 | Approved | JACK KARGODORIAN |
| Final | 9/4/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/4/2024 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 9/4/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 9/4/2024 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/4/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 9/4/2024 | Approved | JACK KARGODORIAN |
| Final | 9/11/2024 | OK to Issue CofO | JACK KARGODORIAN |