10331 S KALMIA ST 90002

Certificate Information: 10331 S KALMIA ST 90002

Application / Permit
23010-10000-00066
Plan Check / Job No.
B23LA00240
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
6'-6" X 8'-8" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 4/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2023 APPLICANT
Assigned to Plan Check Engineer 1/17/2023 JEROME MAGAT PALMA
Corrections Issued 1/18/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 2/3/2023 JEROME MAGAT PALMA
Plan Check Approved 2/7/2023 JEROME MAGAT PALMA
Issued 2/9/2023 APPLICANT
CofO in Progress 3/18/2026 ANSON MAGLASANG
Permit Finaled 4/1/2026 ANSON MAGLASANG
CofO Issued 4/1/2026 ANSON MAGLASANG
Permit Finaled 4/1/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/25/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/27/2023 AMAAN MALIK
Sewer availability Cleared 1/27/2023 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2024 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 8/30/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 8/30/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 8/30/2024 Approved BEN MOLSTAD
Pre-Inspection 8/30/2024 Approved BEN MOLSTAD
Service/Power Release 8/30/2024 Not Ready for Inspection BEN MOLSTAD
Wood Frame 8/30/2024 Not Ready for Inspection BEN MOLSTAD
Pre-Inspection 7/21/2025 Partial Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/6/2025 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 8/6/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/2/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/11/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 10/10/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 10/10/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 10/10/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 10/14/2025 Partial Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Partial Approval JOSEPH MCGARRY
Insulation 10/16/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 10/20/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 10/20/2025 Approved ANTHONY EGSON
Green Building Rough 10/20/2025 Approved ANTHONY EGSON
PLUMBING-Rough 10/20/2025 Approved ANTHONY EGSON
Insulation 10/24/2025 Approved ANTHONY EGSON
Drywall Nailing 10/28/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/4/2025 Approved ANTHONY EGSON
Shower Pan 11/4/2025 Not Ready for Inspection ANTHONY EGSON
Shower Pan 11/10/2025 Partial Inspection ANTHONY EGSON
Final 12/16/2025 Partial Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 12/16/2025 Approved ARTHUR NEGRETE
Green Building Final 12/16/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Not Required ARTHUR NEGRETE
Smoke Detectors 12/16/2025 Approved ARTHUR NEGRETE
Final 12/22/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 12/22/2025 Approved ARTHUR NEGRETE