10331 S KALMIA ST 90002
Certificate Information: 10331 S KALMIA ST 90002
- Application / Permit
- 23010-10000-00066
- Plan Check / Job No.
- B23LA00240
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 6'-6" X 8'-8" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 4/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 1/18/2023 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/3/2023 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/7/2023 | JEROME MAGAT PALMA |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 3/18/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/1/2026 | ANSON MAGLASANG |
| CofO Issued | 4/1/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/1/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/27/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2024 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 8/30/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 8/30/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 8/30/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 8/30/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 8/30/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 7/21/2025 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/6/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/2/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/11/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/14/2025 | Partial Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 10/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/20/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/20/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/20/2025 | Approved | ANTHONY EGSON |
| Insulation | 10/24/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/28/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/4/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 11/4/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 11/10/2025 | Partial Inspection | ANTHONY EGSON |
| Final | 12/16/2025 | Partial Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 12/16/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 12/16/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Required | ARTHUR NEGRETE |
| Smoke Detectors | 12/16/2025 | Approved | ARTHUR NEGRETE |
| Final | 12/22/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 12/22/2025 | Approved | ARTHUR NEGRETE |