3653 S BARRINGTON AVE 90066

Certificate Information: 3653 S BARRINGTON AVE 90066

Application / Permit
23010-10000-00064
Plan Check / Job No.
B22LA26829
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW 32' X 22' DETACHED 1-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK DONE PER ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
Issued on 10/4/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/13/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 GURUNATH NESARAJAH
Corrections Issued 1/29/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 8/17/2023 ARSALAN SHABESTARI
Plan Check Approved 9/6/2023 ARSALAN SHABESTARI
Issued 10/4/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/30/2023 DINAH GARIN
Grading Pre-Inspection Cleared 4/7/2023 KIRK LINKLATER
Stormwater Pollution Mitigatn Cleared 5/30/2023 ANTHONY VARGAS
Eng Process Fee Ord 176,300 Cleared 6/23/2023 DINAH GARIN
Sewer availability Cleared 6/23/2023 DINAH GARIN
Specific Plan Cleared 7/5/2023 JOSHUA JONES
Roof/Waste drainage to street Cleared 7/13/2023 DINAH GARIN
ZI Cleared 8/22/2023 JAZMIN ROQUE
ZI Cleared 8/22/2023 JAZMIN ROQUE
GPI Written Notices Cleared 9/6/2023 GURUNATH NESARAJAH

Contact Information

Architect Goodarzi,, Morteza; Lic. No.: NA23941       ,
Contractor Areio Inc; Lic. No.: 997015-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/29/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 1/9/2024 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 5/9/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Approved JESUS PINEDA
PLUMBING-Rough 5/9/2024 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 6/17/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 6/17/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 6/18/2024 Approved JESUS PINEDA
Insulation 7/11/2024 Corrections Issued JESUS PINEDA
Underground Mechanical 7/11/2024 Approved JESUS PINEDA
HVAC-Rough 7/16/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 7/23/2024 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 8/5/2024 Corrections Issued JESUS PINEDA
Green Building Rough 8/5/2024 Approved JESUS PINEDA
Insulation 8/5/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 8/5/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 9/6/2024 Corrections Issued DANIEL VERA
Drywall Nailing 9/18/2024 Approved MICHAEL ALLEN
Shower Pan 10/2/2024 Approved DANIEL VERA
Interior/Exterior Lathing 10/23/2024 Approved DANIEL VERA
ELECTRICAL-Final 12/5/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 12/5/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 12/9/2024 Corrections Issued DANIEL VERA
HVAC-Rough 12/9/2024 Approved DANIEL VERA
HVAC-Final 12/16/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 12/19/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 3/3/2026 Not Ready for Inspection ARAM AVEDISIAN
Final 3/3/2026 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 3/3/2026 Approved ARAM AVEDISIAN
Green Building Final 3/3/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 3/3/2026 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/3/2026 Approved ARAM AVEDISIAN