17926 W ACRE ST 91325
Certificate Information: 17926 W ACRE ST 91325
- Application / Permit
- 23010-10000-00056
- Plan Check / Job No.
- B23LA00204
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU per LAMC 12.22 A.33 (c)-(d) with entry porch
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2023 | VICTOR CHEN |
| Corrections Issued | 1/17/2023 | VICTOR CHEN |
| Plan Check Approved | 1/12/2024 | JOSEPH RAFOLS |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 5/22/2026 | DAVID MATSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | NIKKI ZULUETA |
| Low Impact Development | Cleared | 1/9/2024 | LUIS CRUZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2024 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 1/11/2024 | NIKKI ZULUETA |
| Sewer availability | Cleared | 1/11/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/26/2024 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 6/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 6/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/10/2024 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/10/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/10/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 7/10/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 7/10/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 7/10/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/12/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/12/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/12/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/11/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/11/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 10/4/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 10/4/2024 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 10/4/2024 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 10/4/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 2/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 2/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 2/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 2/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 3/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 3/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 3/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 3/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/27/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 6/27/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 9/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 9/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 9/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Service/Power Release | 9/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 3/12/2026 | Corrections Issued | KEVIN BERBERYAN |
| Final | 5/11/2026 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 5/11/2026 | Approved | DAVID MATSON |