5019 E RANGE VIEW AVE 90042
Certificate Information: 5019 E RANGE VIEW AVE 90042
- Application / Permit
- 23010-10000-00046
- Plan Check / Job No.
- B23LA00143
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (eplan) NEW DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 5/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | YOUNG KIM |
| Corrections Issued | 3/4/2023 | KHEDER ALRAZAA |
| Quality Review Completed | 3/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/23/2023 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 12/14/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/5/2024 | YOUNG KIM |
| Applicant returned to address corrections | 4/9/2024 | YOUNG KIM |
| Plan Check Approved | 4/25/2024 | YOUNG KIM |
| Plan Check Approved | 4/26/2024 | YOUNG KIM |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 3/24/2025 | DAVID WILLIAMS |
| No Progress | 4/6/2025 | DEROLD HAUFF |
| CofO in Progress | 4/6/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
| CofO Issued | 5/10/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/15/2023 | RUEL COLE |
| Address approval | Cleared | 8/17/2023 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/5/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 2/20/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/2/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/9/2024 | KHEDER ALRAZAA |
| GPI Written Notices | Cleared | 4/18/2024 | KHEDER ALRAZAA |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 5/31/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/31/2024 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 5/31/2024 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 6/10/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 6/11/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/12/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Deputy Wood Construction | 9/25/2024 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/25/2024 | Partial Approval | ROY SPAULDING |
| HVAC-Rough | 9/25/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/25/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 9/25/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 9/27/2024 | Approved | ROY SPAULDING |
| Insulation | 10/8/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/8/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/15/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/15/2024 | Approved | ROY SPAULDING |
| Service/Power Release | 2/20/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/27/2025 | Approved | LILIANA PORTILLO |
| Final | 2/27/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 2/27/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/27/2025 | Approved | LILIANA PORTILLO |
| Final | 3/21/2025 | OK to Issue CofO | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 3/21/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 3/21/2025 | Approved | DAVID WILLIAMS |