1572 1/2 N MYRA AVE 90027
Certificate Information: 1572 1/2 N MYRA AVE 90027
- Application / Permit
- 23010-10000-00019
- Plan Check / Job No.
- B22LA24032
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - (n) detached 1-story ADU per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33 (c)(d)(g), factory-built (state-approved) housing. 2 of 2
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | KELVIN CHUONG |
| Corrections Issued | 1/4/2023 | KELVIN CHUONG |
| Quality Review Completed | 1/6/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/31/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 2/2/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 3/20/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 3/22/2023 | KELVIN CHUONG |
| Plan Check Approved | 3/30/2023 | KELVIN CHUONG |
| Issued | 3/30/2023 | APPLICANT |
| CofO in Progress | 10/16/2023 | JOSEPH MCGARRY |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/12/2023 | MICHAEL SOTO |
| Address approval | Cleared | 2/22/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 2/22/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 2/22/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 2/22/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 2/22/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 2/22/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 2/22/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/1/2023 | AMAAN MALIK |
| GPI Written Notices | Cleared | 3/30/2023 | KELVIN CHUONG |
| Grading Pre-Inspection | Cleared | 3/30/2023 | KELVIN CHUONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/24/2023 | Conditional Approval | JOSEPH MCGARRY |
| Piling/Pier/Caisson | 4/24/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/8/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/8/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Sewer | 5/8/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 5/8/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/11/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/11/2023 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 5/11/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 8/1/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/18/2023 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 8/18/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 8/18/2023 | Approved | JOSEPH MCGARRY |
| Final | 8/18/2023 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/18/2023 | Approved | JOSEPH MCGARRY |
| Green Building Final | 8/18/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/18/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 8/18/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 8/18/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 8/18/2023 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 8/18/2023 | Approved | JOSEPH MCGARRY |
| Structural Steel Frame | 8/18/2023 | Conditional Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 8/18/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | JOSEPH MCGARRY |
| Final | 10/10/2023 | OK to Issue CofO | JOSEPH MCGARRY |
| Structural Steel Frame | 10/10/2023 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/10/2023 | Approved | JOSEPH MCGARRY |