506 N CARMELINA AVE 90049

Certificate Information: 506 N CARMELINA AVE 90049

Application / Permit
22047-30000-01957
Plan Check / Job No.
B22WL03631
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool with spa within the pool and raised deck over piles
Permit Issued
Issued on 2/11/2023
Issuing Office
Current Status
CofO Issued on 3/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 REZA HAGHIGHAT
Corrections Issued 10/2/2022 REZA HAGHIGHAT
Quality Review Completed 10/4/2022 CHIHARU SUZUKI
Building Plans Picked Up 10/5/2022 APPLICANT
Applicant returned to address corrections 1/3/2023 REZA HAGHIGHAT
Plan Check Approved 1/24/2023 REZA HAGHIGHAT
Issued 2/11/2023 APPLICANT
CofO in Progress 3/14/2025 KEVIN SARGSYAN
Permit Finaled 3/27/2025 RICHARD STEINBACH
CofO Issued 3/27/2025 RICHARD STEINBACH
Permit Finaled 3/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/29/2022 REZA HAGHIGHAT
Low Impact Development Cleared 11/29/2022 SARAH YOUSSEF
Construction near power lines Cleared 2/11/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 120 W WILSON AVE 1550      GLENDALE, CA 91203
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/2/2023 Partial Inspection KEVIN SARGSYAN
Deputy Other (see comments) 3/3/2023 Approved KEVIN SARGSYAN
Piling/Pier/Caisson 3/3/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/4/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval KEVIN SARGSYAN
Pre-Gunite 4/18/2023 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 4/18/2023 Partial Approval KEVIN SARGSYAN
Rough-Plumbing 4/18/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/26/2023 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Final 12/3/2024 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 12/3/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 12/3/2024 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 12/13/2024 Approved KEVIN SARGSYAN
Grounding or Bonding 12/13/2024 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/28/2025 Approved KEVIN SARGSYAN
Final 2/28/2025 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 2/28/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved KEVIN SARGSYAN
Equipment Noise Level 3/4/2025 Approved EUSEBIO GUZMAN
Final 3/13/2025 OK to Issue CofO KEVIN SARGSYAN