506 N CARMELINA AVE 90049
Certificate Information: 506 N CARMELINA AVE 90049
- Application / Permit
- 22047-30000-01957
- Plan Check / Job No.
- B22WL03631
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool with spa within the pool and raised deck over piles
- Permit Issued
- Issued on 2/11/2023
- Issuing Office
- Current Status
- CofO Issued on 3/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | REZA HAGHIGHAT |
| Corrections Issued | 10/2/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 10/4/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Applicant returned to address corrections | 1/3/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 1/24/2023 | REZA HAGHIGHAT |
| Issued | 2/11/2023 | APPLICANT |
| CofO in Progress | 3/14/2025 | KEVIN SARGSYAN |
| Permit Finaled | 3/27/2025 | RICHARD STEINBACH |
| CofO Issued | 3/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/29/2022 | REZA HAGHIGHAT |
| Low Impact Development | Cleared | 11/29/2022 | SARAH YOUSSEF |
| Construction near power lines | Cleared | 2/11/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/2/2023 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Other (see comments) | 3/3/2023 | Approved | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 3/3/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Pre-Gunite | 4/18/2023 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 4/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Rough-Plumbing | 4/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2023 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/3/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 12/3/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 12/3/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 12/13/2024 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 12/13/2024 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Approved | KEVIN SARGSYAN |
| Final | 2/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 2/28/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Equipment Noise Level | 3/4/2025 | Approved | EUSEBIO GUZMAN |
| Final | 3/13/2025 | OK to Issue CofO | KEVIN SARGSYAN |