2804 N WESTBROOK AVE 90046
Certificate Information: 2804 N WESTBROOK AVE 90046
- Application / Permit
- 22047-30000-01658
- Plan Check / Job No.
- B22WL03059
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool/spa on piles with cantilever deck *** 1 of 2 ***
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- Issued on 1/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | MONICA RAMIREZ |
| Corrections Issued | 9/6/2022 | MONICA RAMIREZ |
| Quality Review Completed | 9/7/2022 | KEN GILL |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| Applicant returned to address corrections | 10/25/2022 | KELVIN CHUONG |
| Plan Check Approved | 1/4/2023 | KELVIN CHUONG |
| Issued | 1/13/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 10/28/2022 | NATHAN ROMINE |
| Miscellaneous | Cleared | 12/15/2022 | ALBERT TAM |
| Grading Pre-Inspection | Cleared | 1/4/2023 | MONICA RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Partial Inspection | STUART CHAPMAN |
| Piling/Pier/Caisson | 6/9/2023 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 6/30/2023 | Approved | DONALD CRICHLOW |
| Pre-Gunite | 6/30/2023 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 6/30/2023 | Corrections Issued | BRIAN SULLIVAN |
| Gas Piping or Gas Test | 8/4/2023 | Approved | RAUL BARAJAS |
| Rough-Plumbing | 8/4/2023 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 8/22/2023 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 9/15/2023 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 9/21/2023 | Approved | RAUL BARAJAS |
| Pool Equipment Noise Test | 10/24/2023 | Not Ready for Inspection | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 10/26/2023 | Approved | STUART CHAPMAN |
| Final | 10/26/2023 | Corrections Issued | STUART CHAPMAN |
| Pool Equipment Noise Test | 10/26/2023 | Approved | ANDEY CHAPARRO |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Approved | STUART CHAPMAN |
| Final | 10/27/2023 | Conditional Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | STUART CHAPMAN |