1342 N STRADELLA ROAD 90077
Certificate Information: 1342 N STRADELLA ROAD 90077
- Application / Permit
- 22047-30000-01397
- Plan Check / Job No.
- B22WL02656
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- pool & spa on piles & grade beams per eng. calcs. *** 2 of 3 ***
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Valley
- Current Status
- Issued on 5/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2022 | KAVIAN REFAHI |
| Corrections Issued | 7/17/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/27/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/29/2022 | APPLICANT |
| Applicant returned to address corrections | 8/16/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/4/2023 | KAVIAN REFAHI |
| Plan Check Approved | 3/27/2024 | KAVIAN REFAHI |
| Issued | 5/30/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/31/2023 | KAVIAN REFAHI |
Contact Information
| Contractor | Z Development Corp; Lic. No.: 596875-B | 5222 WINNETKA AVE WOODLAND HILLS, CA 91364 |
| Engineer | Salehipour,, Sassan Abolghasem; Lic. No.: C44172 | 1290 NORTH LAKE AVENUE STE 204 PASADENA, CA 91104 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Geologist | Hill,, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/24/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 12/26/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Partial Approval | SEAN HAUPT |
| Deputy Other (see comments) | 2/24/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 2/25/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 2/27/2025 | Partial Approval | CARLOS MATAMOROS |
| Deputy Other (see comments) | 2/28/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/27/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 11/3/2025 | Conditional Approval | ANDREW NAVE |
| Pre-Inspection | 1/26/2026 | Partial Inspection | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 3/27/2026 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 3/27/2026 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 3/27/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/2/2026 | Approved | CHRISTOPHER WILSON |
| Grounding or Bonding | 4/2/2026 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 4/2/2026 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 4/2/2026 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 4/2/2026 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 4/2/2026 | Partial Approval | CHRISTOPHER WILSON |