1911 N SUNSET PLAZA DR 90069

Certificate Information: 1911 N SUNSET PLAZA DR 90069

Application / Permit
22047-30000-00905
Plan Check / Job No.
B22WL01814
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
revised existing attached deck to add (n) pool and spa per engineer's design/details. No new grading.
Permit Issued
Issued on 9/27/2022
Issuing Office
Current Status
CofO Issued on 6/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 YASHAR EMAMI
Corrections Issued 6/13/2022 YASHAR EMAMI
Quality Review Completed 6/19/2022 KAVIAN REFAHI
Applicant returned to address corrections 9/6/2022 YASHAR EMAMI
Plan Check Approved 9/22/2022 YASHAR EMAMI
Issued 9/27/2022 APPLICANT
Building Plans Picked Up 9/29/2022 APPLICANT
CofO in Progress 6/4/2024 BRIAN SULLIVAN
Permit Finaled 6/28/2024 RONALD MYRICK
CofO Issued 6/28/2024 RONALD MYRICK
Permit Finaled 6/28/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/22/2022 YASHAR EMAMI

Contact Information

Architect Elmanovich,, Vladimir; Lic. No.: C25822 16987 ENCINO HILLS DRIVE      ENCINO, CA 91436
Contractor Owner-Builder       ,
Engineer Balshem,, Efim Bercovich; Lic. No.: C34313 1125 16TH ST UNIT 5      SANTA MONICA, CA 90403

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 7/27/2023 Conditional Approval RAUL BARAJAS
Enclosure/Fence 1/4/2024 Approved RAUL BARAJAS
Pool Equipment Noise Test 2/2/2024 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 2/12/2024 Approved RAUL BARAJAS
Final 2/12/2024 Corrections Issued RAUL BARAJAS
Pre-Gunite 2/12/2024 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Ready RAUL BARAJAS
Final 2/23/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved RAUL BARAJAS
Final 6/4/2024 OK to Issue CofO RAUL BARAJAS