10944 W AYRES AVE 90064

Certificate Information: 10944 W AYRES AVE 90064

Application / Permit
22047-30000-00591
Plan Check / Job No.
B22WL01166
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) swimmimg pool and spa per standart plan # 268 *** 1 of 2 ***
Permit Issued
Issued on 9/12/2022
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 EDWIN ESPIN
Corrections Issued 3/25/2022 EDWIN ESPIN
Applicant returned to address corrections 7/25/2022 EDWIN ESPIN
Applicant returned to address corrections 8/25/2022 JASON JANGADA
Building Plans Picked Up 8/30/2022 APPLICANT
Plan Check Approved 9/6/2022 EDWIN ESPIN
Issued 9/12/2022 APPLICANT
CofO in Progress 6/6/2023 JOHNNY MIRANDA
Permit Finaled 6/7/2023 DANIEL ORRANTE
CofO Issued 6/7/2023 DANIEL ORRANTE
Permit Finaled 6/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 8/18/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/12/2022 EDWIN ESPIN

Contact Information

Contractor Decardo'S Pools And Landscape Inc; Lic. No.: 532429-B 23705 VANOWEN ST #114      WEST HILLS, CA 91307
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2022 Approved ASHLEY THOMPSON
Gas Piping or Gas Test 11/28/2022 Approved ASHLEY THOMPSON
Pool Piping 11/28/2022 Approved ASHLEY THOMPSON
Rough-Electrical 11/28/2022 Approved ASHLEY THOMPSON
Rough-Plumbing 11/28/2022 Approved ASHLEY THOMPSON
Deputy Shotcrete 12/7/2022 Conditional Approval JOHNNY MIRANDA
Deck 2/10/2023 Approved JOHNNY MIRANDA
Enclosure/Fence 3/10/2023 Approved JOHNNY MIRANDA
Pool Equipment Noise Test 4/11/2023 Approved JUAN ESCOTO DELGADO
Final 6/2/2023 Conditional Approval JOHNNY MIRANDA
Pre-Gunite 6/2/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved JOHNNY MIRANDA