2763 S MCCONNELL DR 90064
Certificate Information: 2763 S MCCONNELL DR 90064
- Application / Permit
- 22047-30000-00575
- Plan Check / Job No.
- B22WL01128
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- swimming pool per engineer's design/details *** 1 of 3 ***
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | KAVIAN REFAHI |
| Corrections Issued | 4/9/2022 | KAVIAN REFAHI |
| Quality Review Completed | 4/12/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Applicant returned to address corrections | 1/19/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/10/2023 | KAVIAN REFAHI |
| Plan Check Approved | 3/15/2023 | KAVIAN REFAHI |
| Issued | 3/29/2023 | APPLICANT |
| CofO in Progress | 2/20/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 2/22/2024 | DANIEL ORRANTE |
| CofO Issued | 2/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/12/2022 | KAVIAN REFAHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | Mason,, Gary; Lic. No.: LA5938 | 12320 ROCHEDALE LANE LOS ANGELES, CA 90049 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gunite | 6/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Pre-Gunite | 7/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Pre-Gunite | 8/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Pre-Gunite | 8/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Pre-Gunite | 9/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Pre-Gunite | 9/12/2023 | Approved | CLAYTON GRAHAM |
| Deck | 11/13/2023 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 12/11/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 12/14/2023 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 1/25/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 1/30/2024 | Approved | JUAN ESCOTO DELGADO |
| Final | 2/16/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | OGANES TARAKHCHYAN |